Decision Notice - Minor Change - RAL21 0026 01 & OPW21 0303 01 [As Published] · RAL21/0026.01
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserve/Reinstatement
31. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
32. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
33. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Site Access and Driveways
34. Driveway crossovers must be constructed generally in accordance with council’s Standard
Drawings RS-049 and RS-050.
35. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf and must be maintained by the developer until established.
36. The following must be complied with during the construction of the required
crossovers/driveways:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete;
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties;
c. The properties’ accesses must be located a minimum of 1m clear of existing power
poles, streetlights or other signage. The developer is responsible for any necessary
relocation of existing services to provide this clearance and must contact the relevant
service authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
37. All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as
defined in Appendix B.
Stormwater Drainage
38. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
39. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g. by blocking or interfering with natural overland flows).
40. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Page 5 of 10
Document Set ID: 22711882
Version: 4, Version Date: 01/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - RAL21 0026 01 & OPW21 0303 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.