Decision Notice - Minor Change - RAL21 0026 01 & OPW21 0303 01 [As Published] · RAL21/0026.01
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
48. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
Final Inspection
49. A final inspection and approval of the works and completed reinstatement works by Council’s
Inspector is required. Please contact Council on 5329 6245 to arrange for the inspection.
5. REFERRAL AGENCIES
Referral Status Referral Agency and Referral Trigger Response
Address
Concurrence SARA at DILGP SARA Schedule 10, Part 4, The agency provided
at DILGP Via MyDAS2 Division 3, Table 1 its response on 12
at https://prod2.dev- (Planning Regulation November 2021
assess.qld.gov.au/suite 2017): Premises (Reference No. 2111-
/ (for assistance, contaminated because of 25753 SRA. A copy of
contact DILGP at 5352 unexploded ordnance the response is
9701 or attached.
email:[email protected]
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
General Advisory Notes
2. As these driveways are private structures, the owner bears full responsibly for the standard
of its construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed generally in accordance with standard drawings RS-
049 and RS-050.
3. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
4. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
5. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Page 7 of 10
Document Set ID: 22711882
Version: 4, Version Date: 01/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - RAL21 0026 01 & OPW21 0303 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.