Council archive · source document
Delegated Report - Code - Planning MCU24 0089 [As Published] · MCU24/0089
7. The use of the landing must not cause any adverse effects on the amenity of the surrounding
areas including changes to light, views, air quality and noise.
8. Vessels berthed/moored at the Landing must be located a minimum of 3.0 metres from the
prolongation of the property boundaries, and clear of the fish habitat area.
9. Vessels must be connected directly to the Landing, and not located side by side or in tandem
with another vessel.
10. All structures must be designed and constructed such that they are free standing within the
waterway and are not connected to or behind the revetment wall
11. All structures must have no detrimental effects on stormwater drains and/or easements.
12. Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the top of the
revetment wall.
13. A rigid handrail must be fitted on one side of the walkway. The handrail must be of an open
design and in accordance with the approved plans.
14. No posts or vertical supports of the proposed jetty are to extend vertically from the structure
unless they provide necessary support for the handrail.
15. No boatlifting devices are to be attached or moored at the jetty structure for the purpose of
elevating a vessel above the water without Council approval.
16. There must be no electrical reticulation system carrying electricity in excess of 24 volts
beyond the revetment wall unless all switches and power outlets are positioned above the
1%AEP flood level.
17. Lighting associated with the use must be designed, installed, operated, and maintained in
accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
18. The jetty is to be used for private purposes only with no commercial operations to be
undertaken.
19. Boat repair activities are not permitted on site.
20. Wastewater and sullage must only be disposed of at approved pumpout facilities.
21. The mooring facility must not be utilised for live-aboard purposes.
22. Any construction and post construction activity is not to impact on the condition of the
waterway, and is to be conducted so as not to breach the Environmental Protection Act EPA
(1994) and the Environmental Protection (Water) Policy 2009.
23. Certification by a Registered Professional Engineer of Queensland that states that the jetty
is constructed in accordance with best practice methods and is structurally sound must be
submitted to Council. This certification must be submitted to Council within three (3) months
of the completion of the works. A final inspection and approval of the structure by Council’s
Inspector is also required. Please contact Council’s Development Assessment Branch on
5329 6500 to arrange the inspection.
24. This approval lapses where the construction of the jetty has not commenced within two (2)
years of the date of issue of the approval, unless application is made and approved by
Council for an extension.
25. After completion, the proposed works must be maintained in a sound state of repair in
accordance with the approved plans
5. REFERRAL AGENCIES
The referral agencies applicable to this application are:
Page 6 of 8
Document Set ID: 23265182
Version: 4, Version Date: 10/10/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU24 0089 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 423 KB (small file)
- File type
No other editions are linked here.