Decision Making Matrix
Noosa Botanic Gardens - Decision Making Matrix
Activity Categories Priority of completion Timeframes
Safety & Accessibility
Customer Experience
Botanical Collection
Infrastructure
Sustainability
Development
Maintenance
Horticultural
Landscape
Education
Short Medium Long
Amenity
Security
Term Term Term
Items High Medium Low (1-2 yrs) (3-5 yrs) (5+ yrs) Budget
Existing items for repair/improvement
Security Cameras, additional * x x
Major paths that have trip hazards to be temporarily repaired prior to finalisation of the Master Plan x x x
*
Improve current entrance and signage - temporary works to improve the legibility of the entrance for the next few years * * x x
Additional electrical plug in points/solar - facilitate temporary food vendors * x x
Upgrade of Lake Edge for canoe entry point (northern parkland) * x x
Lake interface/stormwater & sediment runoff * x x
Improvements to the dinosaur dig area, needs additional play value * * * x x
Existing trees to be identified for pruning from a horticultural point of view i.e. correct pruning for the specific species * x x
Clearing out of beds that are marked for a particular genus. Replanting with nominated genus species. * x x
Trees to be underprunned to improve views to Lake MacDonald * * * x
Improvements to educational signage * * x x
Improvements to botanical signage * * x x x
New items required/desired/planned for
Security Fence, with lockable vehicle and pedestrian gates to the front boundary and northern boundary * x x
Seating with backs and arm rests to improve accessible seating options * * x x
Existing trees to be identified for pruning from a safety point of view * * x x
Picnic settings that allow for wheelchairs/wheelie walkers to pull up to table * * x x
ft
Lighting to specifically improve safety * x x
Hardworks improvements - paving, large boulders, steps, walls * x x
Internet/qr codes * * x x
Holiday activities/brochures/sheets * * x x
Educational Tours/botanical/science/water * * x x
Green waste/composting * x x
Water/water tanks * x x
Carbon neutral gardens * x x
Solar panels/daisies * x x
Solar panels for electric vehicles/mowers/buggy/small plant/air con. * x x
New or adjusted operational processes
Garden plans - planning for specific improvements to garden beds * * * x x
Decision making criteria prioritisation Priority Mapping
Impact on Activity Category /s
Planned for in the masterplan or included in other Corporate Plans
Security risk improvement
Safety risk improvement
Capital & Resource Cost
ra
Ongoing operation and maintenance costs, whole of life cost
Budget availability & funding opportunity
Capital New or End of life replacement/renewal/deletion
Revenue / Return on investment
Extension of current operational activities
D
683_O2LA_NBG Decision Making Matrix.xlsx Page 1 of 1
NOOSA BOTANIC GARDENS
MASTERPLAN
13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.