INTEGRATED PLANNING ACT 1997 Part D, Version 3.2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mandatory Information _ oe
6. Confirm that the following mandatory information accompanies this application:
Confirmation of
lodgement Method of lodgement
{For all applications
(i) Plans showing the nature and location of the proposed use on the premises and a statement about the
intensity and scale of the proposed use (e.g. number of employees, days and hours of aperation, number of visitors, x Confirmed over the counter
number of seats, capacity of storage area)
When the application involves reuse of existing buildings
(i) Plans showing the size and location of the buildings to be reused [_] Confirmed
[x] Not applicable
When the application involves new building work
(tii) Plans showing the size and location of the proposed new building work x] Confirmed
over the counter
[_] Not applicable
When the application involves reuse of other existing works OO , ae
{iv) Plans showing the nature and location of the works to be reused [ ] Confirmed
[<] Not applicable
When the application involves new operationai work
(v) Plans showing the nature and location of the proposed new operational works x] Confirmed
over the counter
["} Not applicable
OFFICE USE ONLY
Date received Reference numbers
Advice for completing Part D
General advice
e Part A must also be completed for ail IDAS development applications.
° The applicant is responsible for answering all questions fully and correctly, unless following a response there is a statement to go directly to
another question.
° When paying fees to the Environmental Protection Agency by electronic funds transfer (EFT} for coastal development applications, use the

process from the information sheet Electronically paying fees to the Environmental! Protection Agency (EPA) and securely attach the form
Electronic Funds Transfer (EFT) payment notification to this application.

 

Q3 A development permit authorises development to occur. A preliminary approval is a step in the approval process and does not authorise
development to occur - a subsequent application for a development permit must be sought.

 

Table D If the MCU application involves operational work that is the building of a retaining wall on the premises, the application is taken also to be for the
operational work if approval for the operational work has not been applied for in this application or in a separate application.

 

 

 

' This form is also used for material change of use assessable against the land use plan for Caims airport land or Mackay airport land. Wherever planning scheme is
mentioned, take it to mean the land use plan for the airport land.

Used in these records

About this file

File size
2.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

09_1490 - MCU - Detached House [As Published].pdf · 2.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.