                                 Figure 5.2 – Music Modelling Results



The modelling results show the pollutant reduction objectives are met for all contaminants listed in Table
5.1. Details of the proposed bio-retention basin are provided in the Stormwater Management Plan
drawing no: SCG 31131- SW1.1 thru SW1.5 (Appendix D).




6.0      STORMWATER QUANTITY


Noosa Shire Council’s Planning Scheme – Noosa Plan 2020, require post development peak flows
leaving the development site will not exceed the pre-development peak flow rates for the required design
storms. Peak flow increases will be minimised by the provision of an On-site Detention (OSD) basin
fitted with a low flow orifice plate to detain a portion of the runoff from the site and limit the peak flow
rates of pre-development levels.




SCG Consulting Engineers                   Page 15                              SCG Ref: 31131(SWMP).RevB

Log in to download the original (SCG 31131(SWM).RevB - REceived 3.3.22.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.