Slope Stability Report 26-5-2019 OPW19-0193
TRUBUILT
SLOPE RISK ASSESSMENT REPORT
Further guidance on earthworks is contained in Australian Geoguide LR8 Hillside Construction.
4.4 Batter Slopes for Cut and Fill
The proposed development includes the requirements to modify levels on the site through earthworks. Note
the performance of slopes is dependent on materials, type of material, slope angle, loading and can change
with time. The following recommendations are made with respect to retaining walls, and/or batter slopes in
cut or fill:
• Fill slopes should be constructed using compacted material that is initially over constructed and the
cut back to the final position, fill slopes should generally be no steeper than 1(V):1.5(H), fill slopes
greater than 5m in total height should be benched to reduce the overall slope length. Modifications
to this recommended batter angle may be approved following inspection and/or design by a suitably
qualified geotechnical engineer;
• Cut slopes in soil should generally be no steeper than 1(V):1.5(H) and slopes greater than 5m in total
height should be benched to reduce the overall slope length. Modifications to this recommended
batter angle may be approved following inspection and/or design by a suitably qualified geotechnical
engineer;
• Cut slopes in weathered and decomposed rock should generally be no steeper than 1(V):1 (H) and
slopes greater than 4m in total height should be benched. Note that if the foliation of the rock is sub
parallel to the slope, the rock should be cut to the prevailing foliation angle for greater stability.
Modifications to this recommended batter angle may be approved following inspection and/or design
by a suitably qualified geotechnical engineer;
• Unless crest drainage will be maintained or comprise self-flushing, trowelled concrete lined drains
then it is recommended that other methods for the control of surface water on slopes be utilised;
• Examples of suitable crest and slope drainage would include grass lined drains that are regularly
mowed with the surrounding grass, drains lined with Concrete Canvas™, trowelled concrete, stone
pitching or wire mattress revetments, paving, concrete or steel drainage channels, or some specialist
geotextile products. Note that it is recommended that drain liners protect the underlying soil from
erosion and include stilling or dissipating features to slow the velocity of flow along and at the outfall
location. The use of timber or natural fibres (hemp, cotton, jute or coir) is not recommended for
permanent drainage features,
• Where crest and slope drainage are formed from fill materials, fill materials should use non-dispersive
soil that is compacted and formed to a suitable batter slope. Drains formed from cut/fill soil should
have battered sides, be appropriately lined and be of suitable size with regards to the catchment area
and characteristics, design storm, method of lining, maintenance and/or effect if the drain overflows;
• The cut and fill batter slopes in soil and weathered or decomposed rock should be protected from the
effects of surface water flow through planting with grass, groundcover, shrubs and small trees.
Generally, plants should have fibrous root and allow undergrowth. Large trees with shallow root
systems, conifers and plants that prevent the development of undergrowth should be avoided;
• Trees and other plants with invasive root systems should not be allowed to grow on cut slopes in rock
as they can result in root wedging and degradation of the slope;
LEONTAKIANAKOS-R-001 Page 14 26 May 2019
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.