Permit
Environmental authority P-EA-100527093
If marine megafauna are observed within 100m of the vessel, dredging must cease
immediately and not recommence until:
1. the marine megafauna are observed to travel beyond the 100m observation
WT7.1 distance; or
2. a 30-minute period has passed since any marine megafauna has been observed in
the 100m observation zone by the appropriately qualified person conducting
monitoring required by condition WT7.0.
Turtle excluder devices must be used on the dredge drag head of any trailing suction hopper
WT8
dredger used.
WT9 No dredging is permitted between July to August, inclusive.
WASTE
All waste generated in carrying out the activity must be reused, recycled or removed to a
W1
facility or designated onsite location(s) that can lawfully accept the waste.
Page 12 of 18 • ESR/2016/3415 • Version 3.00 • Last reviewed: 29 MAR 2023 Department of Environment and Science
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.