Permit
Environmental authority P-EA-100527093
Conditions of environmental authority
GENERAL
The activity authorised under this environmental authority must be conducted in accordance
with the following limitations:
a) dredging is limited to capital dredging for the purpose of the Noosa River Dredging
project;
b) dredging may only occur in accordance with the following plans:
i. Noosa River Dredging – Scheme of Works, prepared by International
Coastal Management dated 27/01/2023, reference NRD-001, revision 1.
ii. Noosa River Dredging – Typical Section, prepared by International Coastal
Management dated 27/01/2023, reference NRD-002, revision 1.
iii. Noosa River Dredging – Plan 1, prepared by International Coastal
Management dated 27/01/2023, reference NRD-003, revision 1.
G1 iv. Noosa River Dredging – Plan 2, prepared by International Coastal
Management dated 27/01/2023, reference NRD-004, revision 1.
v. Noosa River Dredging – Plan 3, prepared by International Coastal
Management dated 27/01/2023, reference NRD-005, revision 1.
vi. Noosa River Dredging – Plan 4, prepared by International Coastal
Management dated 27/01/2023, reference NRD-006, revision 1.
vii. Noosa River Dredging – Plan 5, prepared by International Coastal
Management dated 27/01/2023, reference NRD-007, revision 1.
viii. Noosa River Dredging – Plan 6, prepared by International Coastal
Management dated 27/01/2023, reference NRD-008, revision 1.
c) all dredged material must only be placed via pipeline to the authorised beach
nourishment locations in accordance with condition G1 (b).
All reasonable and practicable measures must be taken to prevent or minimise
G2
environmental harm caused, or likely to be caused, by the activities.
Unless specifically authorised by a condition of this environmental authority, this
environmental authority does not authorise a relevant act which is:
a) an act that causes serious or material environmental harm or an environmental
G3 nuisance; or
b) an act that contravenes a noise standard; or
c) a deposit of a contaminant, or release of stormwater run-off, mentioned in section 440ZG
of the Environmental Protection Act 1994.
Contravention of conditions
Unless specifically authorised by a condition of this environmental authority, details of any
contravention of a condition of this environmental authority must:
G4.0 a) be reported to the administering authority within 24 hours of becoming aware of the
contravention; and
b) include the nature and circumstances of the contravention and any immediate actions
taken.
Page 5 of 18 • ESR/2016/3415 • Version 3.00 • Last reviewed: 29 MAR 2023 Department of Environment and Science
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.