5.0 State assessment and other matters
5.1 State interests
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning
instruments to the extent they are relevant to the development:
State Planning Policy
South East Queensland Regional Plan
Planning Regulation 2017
State Planning Policy
The Noosa Plan 2020 is generally consistent with the State Planning Policy July 2017 (SPP) except in relation
to:
Natural Hazards, Risk and resilience - Coastal Hazards – in part.
The Noosa Plan 2020 notes that development in the erosion prone area will be subject to assessment against
the assessment benchmarks - natural hazards, risk and resilience. The footnotes for the section detail:
Note: These assessment benchmarks apply only where the chief executive is not identified as a referral agency
under the Planning Regulation 2017.
Schedule 10 of the Planning Regulation details that a reconfiguration of a lot in in a costal management district
and within an erosion prone area requires referral to the Chief Executive.
South East Queensland Regional Plan
The South East Queensland Regional Plan includes the site in an urban area and no further assessment under
the Plan is required.
Planning Regulation
The site is mapped as being contained in an Erosion Prone Area and Coastal Management District and will
trigger referral to the State. .
martoo consulting
town planners + urban designers + development managers page 10 of 12
[OCR of page images]
proposal report
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning
instruments to the extent they are relevant to the development:
¢ State Planning Policy
e South East Queensland Regional Plan
e Planning Regulation 2017
State Planning Policy
The Noosa Plan 2020 is generally consistent with the State Planning Policy July 2017 (SPP) except in relation
to:
e Natural Hazards, Risk and resilience - Coastal Hazards — in part.
The Noosa Plan 2020 notes that development in the erosion prone area will be subject to assessment against
the assessment benchmarks - natural hazards, risk and resilience. The footnotes for the section detail:
Note: These assessment benchmarks apply only where the chief executive is not identified as a referral agency
under the Planning Regulation 2017.
Schedule 10 of the Planning Regulation details that a reconfiguration of a lot in in a costal management district
and within an erosion prone area requires referral to the Chief Executive.
South East Queensland Regional Plan
The South East Queensland Regional Plan includes the site in an urban area and no further assessment under
the Plan is required.
Planning Regulation
The site is mapped as being contained in an Erosion Prone Area and Coastal Management District and will
trigger referral to the State. .
martoo consulting
Marto town planners + urban designers + development managers page 10 of 12
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Proposal Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.