Delegated Report - Code - Planning OPW20 0132

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Coordinator Engineering, Mark Lewis
Development Assessment

APPLICATION DETAILS
Application No.	OPW20/0132
Applicant	Murray John Kahler & Sandreine Kym Kahler
Proposal	Operational Works - Vehicle Crossover
Properly Made Date	23 September 2020
Information Request Date	28 September 2020
Information Response Date	No Response Received
Decision Due Date	11 May 2021
Report Completed Date	11 May 2021
Report Reviewed By	Laurie Schreck

PROPERTY DETAILS
Property Address	7 Allambi Rise Noosa Heads Qld 4567
RP Description	Lot 63 RP 52918
Land Area	885.0000 m²
Existing Use of Land	Residential

STATUTORY DETAILS
SEQRP Designation	Urban Footprint
Zone	Low Density Residential
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	Landslide
Assessment Type	Code
PROPOSAL
The application seeks approval for Operational Works - Vehicle Crossover.
The locality and proposal plan are included below.

Figure 1 – Locality

Figure 2 – Proposal Plan
site details
Background
The application was required to address condition 11 of the associated RAP17/0512.
assessment
Initial assessment of the subject application indicated that a further information request was required. This request was sent on 28 September 2020 and the items related to driveway grades (scraping) and retaining structures.
The applicant requested to “stop the current period” a number of times during the information request period but did not provide any response and the application moved into the Decision Period. The applicant has not responded to a number of emails during the decision period.
It is noted that the driveway had been constructed during late 2020 (aerial photos). A recent site inspection found that:
the driveway was constructed generally in accordance with the originally submitted plan,
the road formation and the driveway did not indicate scraping was occurring,
the extent of retaining structures was limited to an area close to the property boundary,
a footpath of separate concrete pads extended from the driveway to the property gate.
It is considered that as the constructed driveway does not create scraping and the retaining wall does not create an unacceptable fall risk it is recommended that the driveway be approved.
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Driveways and Carparking Code;
The application has been found to generally comply with all applicable statutory instruments.
cONSULTATION
Referral Agencies
Not Applicable
Internal Council Referrals
Not applicable
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW20/0132  for Operational Works - Vehicle Crossover situated at 7 Allambi Rise Noosa Heads Qld 4567 and described as Lot 63 RP 52918, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW20/0132
Street address:	7 Allambi Rise Noosa Heads Qld 4567
Real property description:	Lot 63 RP 52918
Planning Scheme:	Noosa Plan 2020 (31 July 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Operational Works - Vehicle Crossover
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
1486 – R01	A	Proposed Driveway prepared by Barlow Shelley	15 June 2020
CURRENCY PERIOD
The Currency Period for this development approval lapses if the conditions have not been met by 11 May 2023, unless an application to extend the currency period is approved by Council.
GENERAL CONDITIONS
Engineering
The principal contractor must have all the appropriate insurance and public liability documentation to carry out the works. The principal contractor is also responsible to ensure that any subcontractors also have the appropriate insurance and public liability documentation.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
The integrity and condition of any existing public or Council infrastructure and services (above ground and/or underground) must not be adversely affected by the proposed works
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
All works must be constructed and work procedure undertaken in accordance with:
the approved plans/documents and conditions detailed in this Decision Notice
all relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
the latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site.
Works within Road Reserves
No removal of street trees is permitted without Council’s prior written approval.
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
All works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles.
Driveways
Driveway crossovers must be constructed generally in accordance Council’s Standard Drawings RS-049 and RS-050
Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established.
The following must be complied with during the construction of the required crossover/driveway:
the driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete.
the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car Parking for longitudinal and crossfall gradients.
the driveway must be constructed so as to not concentrate or direct stormwater runoff onto neighbouring properties
underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway
where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path
have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset, unless a written approval is obtained from Unitywater/Energex/Telstra and submitted to Council.
any stormwater kerb outlet in close proximity to the edge of the new driveway must be provided with an approved kerb adaptor
any existing kerb sections requiring removal due to the works must be saw-cut and removed to allow for a smooth and neat finish with the new driveway
Pavement design for privately owned works must be undertaken in accordance with the relevant standards.  Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer.
Stormwater Drainage
The constructed driveway must not cause additional ponding on the road formation or the road reserve.
Environment (Erosion and Sediment Control)
Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
The contractor must ensure non-essential exposure of soil is prevented by restricting the extent of works and minimising the duration of soil exposure to adverse weather conditions. Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and prior to any predicted rainfall occurring.
Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes).
FOLLOWING CONSTRUCTION
A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection.
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the requirements of this Operational Works permit.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction.
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ.  The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 7 of 7

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image1.jpeg (image text)]
    
   
   
    

18
‘OBUP1235

2
2RP168314

      

| asne2016|

19
24RP52918, 9,
TRE 165518) i /23RP52918.

     

a
63RP52918
Noosa slay

    
  
 

5
62RP52918

6

‘2RPRBS7S
at

‘OBUP9925

     

"sonbdaoe 89
' 40RP52918 |

 


[Attachment: image2.jpeg (image text)]
 
   

 

 

 
  

 

 

 

 

 

PROPERTY DESCRIPTION
Let63.0n SPs2018,

Ste Awa = 8860?

LEGEND

ee ed

 

 

 

 

 

 
 

 

 

 

 

 

 

 

 

 

 

BASEMENT
aiaiae ee
| |
LEGEND
DRIVEWAY LAYOUT PLAN
ref fo 7]
E Ye te tet
Mey eet, te nme
DRIVEWAY LONGITUDINAL SECTION - SOUTHERN SIDE
DRIVEWAY LONGITUDINAL SECTION - NORTHERN SIDE
[ow] omoomron & [omsfonawna oevans| Scat “APPROVED lw rerecce arseenas cesopmenr
be allie ar ALLAMBI RISE: NOOSA HEADS
sete ems i ORF ell ley FOR M & 5 KAHLER mere 4S
oI secre si cae PROPOSED DRIVEWAY moe |

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
Log in to download the original file

Delegated Report - Code - Planning OPW20 0132.docx · 278 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.