INFRASTRUCTURE CHARGES INFORMATION NOTICE
1. PRELIMINARY
Infrastructure charges are triggered and issued on development approvals as a contribution towards the
cost of "trunk" infrastructure provided to service development.
For development approved prior to 1 July 2011, infrastructure contributions and (ICP) charges continue to
apply in accordance with the development approval conditions and or infrastructure charge notices (ICP)
issued under legislation current at the time those approvals & charge notices were issued.
For development approved from 1 July 2011, adopted infrastructure charges are governed by local
government adopted infrastructure charges resolutions in accordance with the "Sustainable Planning Act
2009 (SPA)" and “State Planning Regulatory Provision (adopted charges) (SPRP)”.
The Sustainable Planning (Infrastructure Charges) and Other Legislation Amendment Bill 2014 introduced
further amendments to SPA that commenced to apply for developments approved from 4 July 2014.
From 1 July 2014, Infrastructure Charges Notices are issued separately by both Council and Unitywater
relating to their specified “Trunk” infrastructure networks. All payments (including contributions & charges
previously issued) are also payable separately to Council and Unitywater respectfully.
2. THE DECISION AND REASONS FOR IT
The Sustainable Planning Act 2009 (as amended), provides for the following:
(1) Authorises local governments to do the following for development approvals:
(a) for trunk infrastructure, either or both of the following—
(i) adopt, by resolution, charges for development infrastructure and levy charges in accordance
with the resolution;
(ii) impose particular conditions about development infrastructure;
(b) for non-trunk infrastructure, impose particular conditions about development infrastructure; and
(2) Provides for a State planning regulatory provision to govern local government adopted charges and
charges by distributor-retailers under the SEQ Water Act for trunk infrastructure.
Noosa Council decided to apply infrastructure charges on development under its adoption of the "Noosa
Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to replace the "Sunshine Coast
Regional Council Adopted Infrastructure Charges Resolution (No.4) 2011" that translated across to Noosa
Council on 1 January 2014. The resolutions also detail the apportionment (break-up) agreement with
Unitywater.
On 12 February 2015, Noosa Council Adopted the "Noosa Shire Council Charges Resolution (No.2) 2014" to
replace the "Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to comply with
the requirements of the SPA amendments dated 4 July 2014 and amended (break-up) agreement with
Unitywater. The resolution takes effect and applies to new approvals issued from Monday 16 February 2015.
3. INFRASTRUCTURE CHARGE NOTICES
3.1 TRIGGERS FOR INFRASTRUCTUE CHARGES & ISSUING OF NOTICES
The triggers for issuing infrastructure charges are defined in the SPA and SPRP and are generally triggered
by the issue of a development permit for either:
(1) Reconfiguration of a lot; or
(2) Material Change of Use of Premises; or
(3) Building Works issued by a Private Certifier.
PO Box 141 P. (07) 5329 6500 [email protected]
TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au ICN - Page 4
[OCR of page images]
PO Box 141, Tewantin, QLD 4565
ea NOLO COLO NONE 22 Silo fi co.as Hi en tea tao. a
INFRASTRUCTURE CHARGES INFORMATION NOTICE
1. PRELIMINARY
Infrastructure charges are triggered and issued on development approvals as a contribution towards the
cost of "trunk" infrastructure provided to service development.
For development approved prior to 1 July 2011, infrastructure contributions and (ICP) charges continue to
apply in accordance with the development approval conditions and or infrastructure charge notices (ICP)
issued under legislation current at the time those approvals & charge notices were issued.
For development approved from 1 July 2011, adopted infrastructure charges are governed by local
government adopted infrastructure charges resolutions in accordance with the "Sustainable Planning Act
2009 (SPA)" and “State Planning Regulatory Provision (adopted charges) (SPRP)".
The Sustainable Planning (Infrastructure Charges) and Other Legislation Amendment Bill 2014 introduced
further amendments to SPA that commenced to apply for developments approved from 4 July 2014.
From 1 July 2014, Infrastructure Charges Notices are issued separately by both Council and Unitywater
relating to their specified “Trunk" infrastructure networks. All payments (including contributions & charges
previously issued) are also payable separately to Council and Unitywater respectfully.
2. THE DECISION AND REASONS FOR IT
The Sustainable Planning Act 2009 (as amended), provides for the following:
(1) Authorises local governments to do the following for development approvals:
(a) for trunk infrastructure, either or both of the following—
(i) adopt, by resolution, charges for development infrastructure and levy charges in accordance
with the resolution;
(ii) impose particular conditions about development infrastructure;
(b) for non-trunk infrastructure, impose particular conditions about development infrastructure; and
(2) Provides for a State planning regulatory provision to govern local government adopted charges and
charges by distributor-retailers under the SEQ Water Act for trunk infrastructure.
Noosa Council decided to apply infrastructure charges on development under its adoption of the "Noosa
Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to replace the "Sunshine Coast
Regional Council Adopted Infrastructure Charges Resolution (No.4) 2011" that translated across to Noosa
Council on 1 January 2014. The resolutions also detail the apportionment (break-up) agreement with
Unitywater.
On 12 February 2015, Noosa Council Adopted the "Noosa Shire Council Charges Resolution (No.2) 2014" to
replace the "Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to comply with
the requirements of the SPA amendments dated 4 July 2014 and amended (break-up) agreement with
Unitywater. The resolution takes effect and applies to new approvals issued from Monday 16 February 2015.
3. INFRASTRUCTURE CHARGE NOTICES
3.1 TRIGGERS FOR INFRASTRUCTUE CHARGES & ISSUING OF NOTICES
The triggers for issuing infrastructure charges are defined in the SPA and SPRP and are generally triggered
by the issue of a development permit for either:
(1) Reconfiguration of a lot: or
(2) Material Change of Use of Premises; or
(3) Building Works issued by a Private Certifier.
ns ~ ~ PO Box 141 P. (07) 5329 6500 [email protected]
NOOSA C OUNCIL TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qid.gov.au ICN - Page 4
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.