Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
1. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are numbered 07/08-1 and 07/08-2, prepared by John Norden and
Associates and dated February 2007 and as may be amended by these conditions and annotations made
on the plans.
2. Structures should be designed and constructed such that they are free standing within the waterway and
are not connected to or behind the revetment wall or rock wall.
3. A rigid handrail shall be fitted on one side of the walkway.
4. No boatlifting devices are to be attached or moored at the jetty structure for the purpose of elevating a vessel
above the water without Council approval.
5. The jetty shall be constructed in a manner to render the underside area vermin proof.
6. There shall be no electrical reticulation system carrying electricity in excess of 24 volts beyond the
revetment wall.
7. Lighting associated with the use shall be designed, installed, operated, and maintained in accordance
with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
8. The jetty is to be used for private purposes only with no commercial operations are to be undertaken.
9. Boat repair activities are not be permitted on site.
10. Wastewater and sullage shall only be disposed of at approved pumpout facilities.
11. The mooring facility shall not be utilised for live-aboard purposes.
12. Any construction and post construction activity is not to impact on the condition of the waterway, and is to
be conducted so as not to breach the Environmental Protection Act (EPA) 1994 and the Environmental
Protection (Water) Policy 1997.
13. The approval or conditions do not constitute a ruling on structural safety and the applicant must make
their own arrangements to ensure adequacy of design and work. Also any approval granted does not
warrant that such plans and specifications have been checked in detail, nor does it absolve the owner of
the land from complying with all the conditions of this approval and/or relevant Council By-Laws and
Policies and/or relevant statutes and/or statutory regulations in the execution and/or performance of said
works. The Council does not accept any responsibility for the accuracy of such plans and specifications
as approved.
14. Certification by a Registered Professional Engineer of Queensland shall be submitted to Council prior to
the return of any bond monies held by Council. The certification shall state that the jetty has been
constructed in accordance with best practice methods, is in accordance with Coastal Protection and
Management Act 1995, is structurally sound and will not have any adverse impacts on or place additional
loads upon the existing revetment wall.
15. A final inspection and approval of the structure by Council’s Inspector is also required prior to the return of
any bond monies held by Council. Please contact Council’s Land Development Section to arrange the
inspection.
16. The jetty shall be licensed with the Council upon completion of the structural work and shall be licensed
annually thereafter.
17. The Development Permit for a material change of use of premises lapses if the use has not happened by
10 July 2009, unless an application to extend the currency is approved by Council.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@20089af2\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00000718.001 [As Published]Related documentApplication case desk ↗
0015673E.001.pdfRelated documentPublic source context ↗
About this file
- File size
- 348 KB (small file)
- File type
No other editions are linked here.