1. SUMMARY
The key points of this investigation are as follows:
1. Runoff from road widening, footpaths and driveway crossovers is to be cleaned of
nutrients and gross pollutants via a Bioretention Basin and then released to existing to
the gully.
2. The increase in pollutant loads due to the increase in impervious areas is to be
attenuated.
3. Water saving devices for new fixtures are required.
4. Stormwater Detention is to be incorporated into the Bioretention Basin to achieve no
increase in runoff concentration.
2. INTRODUCTION
This report was written as part of an Reconfiguration of a Lot application Information Request
for Sunshine Coast Regional Council:
Submit a preliminary Storm water Management Plan (SMP)showing how stormwater
from the development will be treated to meet current best practice load based reduction
targets and how peak discharge will be limited to pre-development rates for all events
from the 1 to 100 year ARI storm events. The preliminary SMP should be designed in
accordance with the preliminary master as a result of Item 1.
As such this Stormwater Management Plan (SMP)has been prepared in accordance with the:
1. Water Sensitive Design Code in the Noosa Plan; and
2. Water Sensitive Urban Design Technical Design Guidelines for South East Queensland,
published by Health Waterways.
The site subject to this report is Lot 136 on MCH978 located at 55 Lake MacDonald Drive,
Cooroy (refer Site Location Plan Figure 1.1).
This SMP considers the new hardstand areas, including road widening, footpath, driveway
crossovers, and new roof areas for the proposed 4 lots. This report also aims to demonstrate
that the proposal complies with relevant codes and guidelines and that the storm water runoff
will not change the surrounding hydrology.
A Bioretention basin is required for the site. This device will enable the water quality objectives
to be achieved. Water minimisation is in accordance with the guidelines.
The Model for Urban Stormwater Improvement Conceptualization (MUSIC)has been used to
assess the suitability of various treatment devices and to model existing and predicted pollution
export loads and concentrations.
5
55 Lake MacDonalld Drive Stage 1
-
SMP Rev I.doc May 2013 1225
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
REFERENCED DOCUMENT - REC13/0015Related documentApplication case desk ↗
About this file
- File size
- 27.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.