5. Final Recommendations
To ensure the successful implementation and long-term performance of the stormwater management system,
the following recommendations are made:
1. Final engineering design verification to confirm basin and pipe network functionality under all
design storm scenarios.
2. Ongoing monitoring and maintenance of bio-retention systems to sustain treatment
performance.
3. Regular review of stormwater infrastructure performance post-development to ensure
compliance with local authority standards.
By incorporating these stormwater management measures, the proposed development will effectively balance
growth with sustainable water management, ensuring long-term resilience against stormwater-related
challenges.
12 GYMPIE STREET, TEWANTIN
Stormwater Management Plan 22
Client Reference: P0198-25-001 4 November 2025
Prepared for Novato Group
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.