06/0933 - Outdoc re: approval of development for Op Works · 142006.933

of 18

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 8

10,

11,

12.

 

 
   

Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION

 

COUNCIL |

 

The development shall be carried out in accordance with Engineering drawings Nos. 0202 —
06,07,08,09,10,11,12,13,16 dated 12 January 2006 and as prepared by Callaghan & Toth or as modified
herein.

The minimum depth of asphalt must be 30mm, which complies with Council's standard.

‘The construction of the jetty and sewerage works as shown on the plans do not form part of this approval.

The total required pavement thickness shall be based on the Department of Transport’s Pavement Design
Manual using soaked CBR tests of the subgrade.

The design pavement thickness, together with CBR test results shall be submitted to Council's Manager -
Land Development for approval prior to placement of pavement materiat.

A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the pre-start
meeting. The pre-start meeting will only be held once Council's Construction Technical Officer has
confirmation that the bond monies have been received by Council.

The bond will be refunded fess any costs incurred by Council in ensuring compliance with these
conditions or any additional inspections incurred for substandard work or work undertaken not in
accordance with this permit.

The names of any proposed contractors for works are to be submitted in writing, together with copies of
current Public Liability and Workers Compensation Insurances, for consideration for approval by the
Manager-Land Development seven (7) days prior to pre-start meetings and commencement of works.

A separate letter will then be issued approving the Contractor (or otherwise) forthe works. No other
Contractor or Subcontractor shall be engaged to carry out the works or any part of the works without the
written approval of the Manager-Land Development.

Council's Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
intention to commence works to arrange a “pre start” meeting regarding the civil works. .

Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council's
signed approved drawings and conditions by the applicant.

The Consulting Engineers for the project shall be currently Registered Professional Engineers of
Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
Council's Construction Technical Officer or nominated staff. Council’s Construction Technical Officer shall
provide an inspection form for signing off by the Engineer at appropriate stages of construction, during on-
site meetings. Construction Technical Officer will also sign the form at each stage when conditions
required have been-satisfied. The works will be accepted “On Maintenance’ after this form, signed by the
inspector for each stage is complete, together with a letter from the Engineer requesting that the works go
“On Maintenance”. .

Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
(This person will be the contact for the project).

Council standards shall apply to these works unless otherwise modified herein.

The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.

NSC p:icivica\documents\dd\01 0Vrom000\0 1 0-2006-00000933-001\0003decnotice.doc

Used in these records

About this file

File size
2.0 MB (small file)
File type
TIF

No other editions are linked here.

Original file

Log in to download the original file

06_0933 - Outdoc re_ approval of development for Op Works.tif · 2.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.