Decision Notice MCU25 0053 & OPW25 0074 (As Published) · OPW25/0074

of 10

Text shows just the words. Original shows the document exactly as it was published.

                      Existing vegetation in the road reserve must be retained, unless written authorisation from
                      Council is granted for the clearing.
                      Fencing
               8.     The maximum height any fences adjoining a residential use must not exceed 2.0m above
                      the natural ground level at any point. Unless is required to satisfy the acoustic condition of
                      this notice and accepted as generally in accordance by Council.
               9.     Street fencing must be provided generally as shown on the Approved Plans, and not exceed
                      1.8 metres in height along Noosa Parade
               10.    The area of land between the fence and the front property boundary must be landscaped to
                      screen the fence from the street. Landscaping must not encroach more than 500 millimetres
                      into the road reserve or within 1.5 metres of a sealed footpath.
                      Property Access and Driveways
               11.    Vehicle access to the subject site is limited to the constructed driveway only. A clause must
                      be included in the contract of sale for the subject site which requires vehicle access to be
                      from the constructed driveway only, and which prohibits the driveway from being relocated
                      without Council agreement.
               12.    Car parking spaces must be provided on site as shown on the approved plans and always
                      made available and accessible for residents. Vehicle manoeuvring areas are to be provided
                      on site in accordance with the Australian Standards for Off-street car parking so vehicles
                      enter and leave the site in a forward gear.
                      Stormwater Drainage
               13.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge without causing scour or damage to the subject site or any adjoining properties.
                      Easements
               14.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               15.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               16.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Geotechnical Stability
               17.    All works must be carried out in accordance with the recommendations contained in PTG
                      Consulting’s Geotechnical Investigation Report (PTG/01608-0001, Rev. 0) dated 28
                      February 2025 and endorsed as part of the building approval.
               18.    A dilapidation survey must be carried out of all adjacent properties, structures and
                      infrastructure prior to the commencement of works and endorsed as part of the building
                      approval.
                      Acid Sulfate Soils
               19.    All works must be carried out in accordance with PTG Consulting’s Acid Sulfate Soil
                      Management Plan (PTG/01608-0002, Rev. 0) dated 11 April 2025 and endorsed as part of
                      the building approval.
                      Dewatering
               20.    All dewatering works must be carried out in accordance with ADG Consulting’s Dewatering
                      Management Plan (ADG1777.25, Rev. 0) dated 1 May 2025 and endorsed as part of the
                      building approval.


                                                                                                      Page 3 of 10
Document Set ID: 24343665
Version: 2, Version Date: 28/11/2025

Used in these records

About this file

File size
171 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice MCU25 0053 & OPW25 0074 (As Published).pdf · 171 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.