ORDINARY MEETING MINUTES 19 JANUARY 2017
54. The canopy installed over FDA must be designed to minimise the amount of rain
entering the dispensing area and must overhang by a horizontal distance of at
least one-quarter of the roof height out from the vertical above the boundary of
the demarcated fuel dispensing area as per drawing B16239-CSK01.
55. Stormwater from roofed areas must be directed away from the FDA catchment.
56. The area within the FDA must be graded and drained to a containment vessel
(or collection sump) with no connection to stormwater or sewer or above ground
detention tank (i.e. a ‘blind sump’). Acceptable materials of construction include
precast concrete with a minimum certified design life of 50 years, designed in
accordance with AS 3600-2009 Concrete structures. Other materials of
construction may be used where approved by Council.
57. The containment vessel must have a capacity to hold a volume equivalent to at
least that of the largest tanker compartment likely to be delivering fuel to the site
plus an allowance for windblown rain (i.e. no less than 10,000litre capacity).
Windblown rain allowance in m3 (Vr) can be calculated using the following
equation: Vr = 0.005 x 3 x Po where Po is the total length of the open perimeter
of the canopy in metres.
58. Signage indicating the rate of flow must be provided for drainage inlets in the
FDA. Examples include 'Flows to blind sump', or 'Flows to containment facility'.
Signage is to be painted or otherwise indicated around the drain inlets.
59. Where fuel deliveries are intended within the FDA, the standing area must be
clearly demarcated and graded to the FDA containment vessel as per drawing
B16239-CSK01.
60. A liquid-tight dispenser sump must be installed under each dispensing unit. It is
to be designed to house all pipework joins and fittings and to collect and contain
any leak from contaminating the surrounding soil/groundwater.
Uncovered Forecourt Area (UFA)
61. All ground surfaces of UFA liable to contamination from vehicular activities must
be constructed of impermeable materials, free of gaps or cracks. Suitable
materials include asphalt, waterproofed, reinforced concrete or an approved
equivalent.
62. Signage indicating the rate of flow must be provided for drainage inlets in the
UFA. Examples may include 'flows to stormwater treatment system' or 'flows to
creek'. Signage is to be painted or otherwise indicated around the drain inlets.
63. Road tanker delivery stands located within the UFA must be clearly demarcated
and sited away from buildings, traffic areas, dispensing areas and emergency
escape routes. The road tanker delivery stand is to be normally drained to the
UFA stormwater quality improvement device (SQUID), however, diversion valves
are to be engaged during fuel delivery operations to divert drainage to the FDA
containment system (blind sump).
Stormwater Quality Improvement Device (SQUID)
64. All stormwater from UFAs must be captured and drained to the approved SQUID.
65. The SQUID (treatment tank/ Stormwater 360 pods filter cartridges & detention
tank) intended to be installed as part of the stormwater drainage system for the
UFA, must incorporate the following design measures as a minimum:
a. steel bars or trash gates with at least 20mm spacing;
b. filtration devices such as sand filters or gross pollutant traps capable of
removing litter (diameter greater than 5mm) and at least 70% of fine
sediments (>125µm).
Page 12 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.