[DAS C-6
Defence advises that development or land use rezoning proposals for land within a ‘substantial’ zone
should only proceed following the conduct of UXO investigation and clearance activities. Defence
maintains a list of commercial UXO investigation and remedial search contractors that it accredits to
carry out this work.
Defence also recommends that owners or occupiers of potentially affected land and workers and
contractors employed on the land need to be aware of the procedure ifa suspect object is found.
As the EPA has no record of the site being further investigated or remediated, it is considered that
there remains a possibility of UXO being found on it.
However, the EPA is also informed of the extent of development that has been carried out on the
site. Because there is no recorded evidence of UXO being found on this site during its development
to date or on adjoining sites that have been similarly developed, it is considered that the potential for
residual UXO to exist on the site is only slight.
4 Conditions
The following concurrence agency conditions are to be attached to any approval:
4.1 Any person employed to work on any excavation, earthworks or soil disturbance related to
the subject development of the site is to be forewamed in writing by the applicant.
This warning is to explain that information available to the EPA indicates a slight potential
for residual UXO exists on the site and work should proceed with due caution. It is to state
the procedure to be followed by any person finding an object suspected of being explosive
ordnance or component thereof:
¢ Do not disturb the object.
e Take action, where appropriate, to prevent it being disturbed by another person.
e Note its approximate dimensions and general appearance.
e Note the route to its location.
* Advise the Police as soon as possible.
4.2. The applicant is to notify the EPA of any UXO or explosive ordnance component found on the
site as soon as possible after such an object is discovered.
4.3. At the completion of any earthworks related to the subject development, a written statement,
signed by the principal contractor, is to be provided by the applicant to the EPA advising of any
evidence of UXO or lack thereof and the extent of earthworks conducted.
4.4 Prior to Condition 4.3 being satisfied, no excavated gravel, rock, sand or soil is to be removed
from the site without written EPA approval.
4.5 The applicant is to advise the owner and any occupier of the site of the above responsibilities.
5 Additional comments or advice
Applicants may contact the EPA’s Contaminated Land Unit on (07) 3224 5644 or visit the Defence
website hitp:/svwiy.defence. gov.a »/ for the details of current UXO investigation and remedial
search contractors. The EPA accepts reports based on investigative and remedial work carried out
by (hese contractors.
VER 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
07/2106 - Referral Agency Reponse - EPA [As Published]Related documentApplication case desk ↗
About this file
- File size
- 225 KB (small file)
- File type
No other editions are linked here.