ADG Consulting Pty Ltd
6 Water quality management
6.1 Responsibility
The Site Manager is ultimately responsible for implementing the water quality management procedures
described in this DMP.
6.2 Operational policy
To prevent impacts on the receiving waters by effectively treating all extracted groundwater prior to
discharge from the site.
6.3 Performance criteria
The performance criteria for the discharge of extracted groundwater are the water quality objectives
provided in Table 2 and Table 3 in Section 4 of this report. Both the discharge and receiving waters (within
a 20 m radius of the stormwater discharge point) will be assessed against the WQOs to ensure that the
environmental values of the waterway are maintained. Receiving waters data will also be assessed
against background monitoring data if non‐compliant results are obtained at the receiving waters
monitoring location.
6.4 Implementation strategy
All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
stormwater network. The treatment system described in Section 6.4.1 will be adopted, installed and
operational prior to the commencement of dewatering.
6.4.1 Groundwater treatment systems
Subject to final appointment of shoring and dewatering contractors (who all generally have different
treatment systems), the following treatment systems are generally proposed for dewatered groundwater
treatment prior to discharge. Regardless of the contractor employed, groundwater treatment systems
should be installed with capability for treating flow rates of up to 8 to 10 L/sec, as a contingency against
higher than anticipated flow rates exceeding the estimated 62 L/sec as a result of varying ground
conditions across the extent of excavation.
Primary treatment
A groundwater treatment system will be installed to provide primary treatment of the extracted
groundwater. The system will provide the following capabilities:
1. A baffled treatment tank with 5 kL minimum capacity
2. Automated in‐line chemical dosing systems for the addition of buffering solutions and coagulants
3. A filtration system to reduce fine particulates (if required)
4. Emergency response alarms for non‐routine situations.
Based on the estimated extraction rate, this system will provide approximately one minute contact time
during the initial chemical dosing, prior to secondary treatment using a sedimentation tank. Primary
treatment tank will be vertically stacked on the secondary treatment tank wherever practicable to
minimise site area required for groundwater treatment equipment.
Secondary treatment
A 23kL sedimentation tank will be utilised to provide the necessary residence time for secondary
treatment of the groundwater prior to discharge to the stormwater system. Based on the estimated
groundwater extraction rate of approximately 223,200 L/hr (equivalent 3,720 L/min) from Section 5.3.1
of this Report, one sedimentation tank will provide approximately three minutes retention time following
primary treatment of the extracted groundwater. This is considered to be sufficient secondary settling /
retention time based on extensive prior experience on other sites in similar ground conditions.
ADG1668.24 Dewatering Management Plan_Rev0_12.07.24 Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.