ADG Consulting Pty Ltd
Monitoring of field parameters in extracted Environmental Environmental
Weekly Consultant
groundwater (pre‐treated) Consultant
Laboratory analysis of samples recovered from Initially, then as Environmental Environmental
extracted groundwater (pre‐treated) required Consultant Consultant
6.6 Maintenance
The groundwater treatment systems must be regularly maintained. Maintenance must include:
Regular cleaning and or replacement of the filters within the filtration unit, where required to be
installed.
Regular removal of sediment from the sedimentation tank. The sediment must be either returned
to the excavation pit for dewatering and bulking out with excavated material or removed from the
site by a licensed liquid waste contractor.
Regular check of the dosing system and top‐up of buffering solutions and flocculants.
6.7 Reporting
Dewatering management procedures and monitoring results will be reviewed by the Environmental
Consultant weekly to ensure that the treatment procedures are effective, and that the receiving waters
are not being impacted by the extracted groundwater being discharged.
The following reporting procedures will be adopted:
A summary report will be prepared upon completion of the initial pre‐discharge monitoring. The
report will be submitted to the Site Manager, Dewatering Contractor, and NSC upon request.
Weekly interim reports will be prepared upon receipt of laboratory data for each round of ongoing
compliance monitoring. The interim reports will display all data obtained during the previous
monitoring event, and provide comments and recommendations based on the results.
A dewatering compliance report will be prepared on completion of the project (upon request).
The above reports will be prepared by the Environmental Consultant and provided to the Site Manager
and Dewatering Contractor as they become available. The reports will include all water quality results
and comparison to the WQOs, corrective actions and recommendations made to the Site Manager and
Dewatering Contractor during the monitoring period.
The Site Manager must keep records of complaints, volumes of chemicals used, and treatment methods
employed. These records must be available on‐site at all times and submitted to NSC by the Site Manager
upon request.
6.8 Contingencies
If water quality monitoring indicates ongoing exceedances of the performance criteria, and the water
quality objectives for the receiving waters cannot be met, then corrective actions will be adopted as
necessary. Possible contingencies may include one or more of the following:
Installation of additional sedimentation tanks to provide increased residence time and assist with
the retention of precipitated iron hydroxides, other heavy metals and/or suspended sediments.
Installation of additional flocculant and/or coagulant dosing systems to assist in precipitation of
suspended sediments and/or heavy metals.
Installation of activated carbon filtration or other fine media filtration to retain suspended
sediments and/or heavy metals.
ADG1668.24 Dewatering Management Plan_Rev0_12.07.24 Page 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.