ADG Consulting Pty Ltd
3 Previous investigations
This DMP is based on site specific information sourced from the following, provided to ADG by Douglas
Partners:
Acid Sulfate Soil Investigation, Proposed Residential Development, 13 Mermaid Quay, Noosaville.
May 2024. Douglas Partners. Ref: 229073.00.R.001.Rev0, 2024‐04‐11.
Geotechnical Investigation, Proposed Residential Development, 13 Mermaid Quay, Noosaville. May
2024. Douglas Partners. Ref: 229073.00.R.001.Rev0, 2024‐04‐11.
Proposed Development – 13 Mermaid Quay, Noosaville, QLD. June 2024. Paul Clout Designs Pty Ltd.
Council Drawing Project Ref: 229073.00, 2024‐06‐05. (Refer Appendix C).
It is noted that dilapidation reports for surrounding structures and services are proposed to be
undertaken prior to commencement of construction and dewatering, however are to be provided to
Council separately from this DMP.
A brief discussion of relevant soil and groundwater conditions is provided below.
3.1 Douglas Partners Geotech Report 2024
A Geotechnical Investigation alongside an Acid Sulfate Soil Investigation was undertaken at the site in
May 2024 (reported July 2024) by Douglas Partners (DP).
3.1.1 Soils
A total of two (2) boreholes (BH01 & BH02) were drilled on the proposed development footprint to
between 1.5 and 6.0 mbgl.
The subsurface profile encountered is generally described as clay and sand fill material at the ground
surface, extending to depths ranging between 1.5 m and 6.0 m. Fill material is underlain by natural sand
which is fine to medium dense throughout the soil profile with traces of silt until the borehole termination
depths.
Alongside the Geotechnical Investigation (2024), Acid Sulfate Soil (ASS) samples were collected at 0.25 m
intervals in BH01 from the surface until 6.0 m & BH02 to from the surface until 1.5 m depth. A total of
thirty (30) samples were collected for ASS screening and six (6) samples were selected for further analysis
by the Chromium Reducible Sulfur suite (CRS).
ADG notes that the testing was limited to two boreholes with ASS testing to 6.0 m depth, and DP reports
that within part of this depth profile the clayey sand and natural sands are considered to contain potential
ASS requiring management of ASS disturbance. All excavated spoil from depths between 1.5 to 6.0 mbgl
within the excavation footprint will need to be appropriately neutralised with lime and validated in
accordance with recommendations by DP in the ASS Investigation Report (DP, 2024), and therefore the
presence of ASS has the potential to impact water quality during dewatering for construction.
3.1.2 Groundwater
During drilling activities for the Preliminary Geotechnical Investigation, groundwater seepage/inflow was
encountered at 0.6 to 1.9 m depth below the ground surface (standing groundwater level was later
measured at 0.58 m in depth in borehole 2)(DP, 2024). ADG notes based on the RLs supplied in the DP
Report that this equates to a maximum groundwater elevation of approximately 0.3 m AHD.
It should be noted however, that groundwater depths and ground moisture conditions are affected by
weather and climatic conditions, tidal variations, surface and subsurface drainage/permeability
conditions, and human influence and will therefore vary with time. Groundwater levels are expected to
be similar to the water level in the canal to the east and river to the north, albeit somewhat a dampened
response to tidal variations.
ADG1668.24 Dewatering Management Plan_Rev0_12.07.24 Page 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.