48. Any damage caused to any public utility (eg pipelines, drainage pits, pathways, roads etc)
during the course of construction shall be repaired to Council’s standards and at no cost to
Council.
49. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
50. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Refuse
51. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and
Industrial Premises”, including an external imperviously paved area correctly sized for all
refuse and recycling containers and suitably screened from public places and neighbouring
properties. A bin wash area is required with a cold-water tap, hose and drain outlet
connected to sewer, via a bucket trap. The drain outlet is to be designed to prevent storm
water entry to the sewerage system and this can be achieved with a nib wall 50mm high and
up to 700mm x 700mm wide (max 0.5m²), or alternatively the waste area can be roofed, or
any other design approved by Council.
52. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
53. A Waste Management Plan (Operational) in accordance with Planning Scheme Policy No. 9
“Waste Management Multi-Dwellings and Commercial and Industrial Premises”, must be
submitted for the day-to-day operation of the development and approved by Council’s Health
Section prior to issue of development permit for operational works.
It is critical that waste areas are properly planned. A copy of Planning Scheme Policy No. 9
explaining exactly how to predict waste quantities and design waste areas is available from
Council and the web. The Plan shall include the following information: -
The types of waste that will be generated from the activities approved within the
development.
Estimated volumes or tonnage of both recyclables and waste generated.
Methods to be used for dealing with garden waste.
Initiatives to minimize waste either by waste prevention, reduction, re-use or recycling.
Description of procedures for getting all waste to the bins; the storage of bins and the
collection of bins by the contractor.
A description of the design details of waste storage and recycling areas including size,
location, elevation and floor plan, methods of bin washing and system to prevent storm
water getting into sewer via the bin wash.
A description of types and volume of waste storage containers to be used.
The waste and recycling storage area shall include the provision of containers for all
waste and recycling materials including putresable matter, non-recycling waste, paper/
cardboard, glass, aluminum/steel cans, waste oil, styrofoam boxes, etc, and bin
washing facilities connected to sewer.
A detailed description of vehicular access to collect waste. Where collection is off
street, access must allow vehicles to enter and leave the site in a forward direction.
54. A Waste Management Plan (construction and demolition) shall be submitted prior to
demolition, removal or relocation of any building other than a shed
Page 8 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Decision Notice - 010.2007.00002446.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 90 KB (small file)
- File type
No other editions are linked here.