Council archive · source document
Idas 23 · OPW16/0098
Attached to the e-mail OPW16/0098 - Operational Works Application.
Table B—Material change of use
a) Does the material change of use involve the following? (Tick all applicable boxes.)
Operational work carried out completely or partly in the coastal management district
b) Does the material change of use involve building work carried out completely or partly in the coastal management
district that is:
the construction of new premises with a gross floor area of at least 1000 m2
the enlargement of the gross floor area of existing premises by more than 1000 m2
Table C—Reconfiguring a lot
a) Does the reconfiguring a lot involve the following? (Tick all applicable boxes.)
Land situated completely or partly in the coastal management district
The construction of a canal
b) How many lots will be created?
Table D—Building work
a) Is the building work on land completely or partly seaward of the coastal building line under the Coastal Protection
and Management Act 1995?
No Yes
3. Is the tidal works located within a local government tidal area? (Tick all applicable boxes)
No Yes—provide details below
Local government: Noosa Shire
Mandatory supporting information
4. Please provide the following information Confirmation of Method of
lodgement lodgement
For all applications
A statement addressing the relevant part(s) of the State Development Confirmed
Assessment Provisions (SDAP). Not applicable
For applications involving operational work that is tidal works
A copy of the certificate of title for the land (including tidal land) that Confirmed
would abut or adjoin the proposed works. Not applicable
Plans showing: Confirmed
the real property description and boundaries of the land (including Not applicable
tidal land) that would abut or adjoin the proposed works
the proposed works (including existing works to be removed) in
relation to relevant tidal planes (e.g. mean high water springs)
the slope angles of the beds and banks of the tidal area and the
finished levels of the proposed works.
For tidal work that will occupy a navigable waterway provide a water Confirmed
allocation area plan providing evidence that the proposed work will not Not applicable
prejudice the access rights of adjoining property owners.
IDAS form 23—Tidal works and development within
the coastal management district
Version 3.1—3 August 2015
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
IDAS 23.pdfRelated documentApplication case desk ↗
About this file
- File size
- 277 KB (small file)
- File type
No other editions are linked here.