ANNUAL PERFORMANCE REPORT INCLUDING Q4 OPERATIONAL PLAN 2023-24 PROGRESS REPORT · Report
Plans and drawings: the text below has words only, no drawings.
GENERAL COMMITTEE MEETING 12 AUGUST 2024
6.7 ANNUAL PERFORMANCE REPORT INCLUDING Q4 OPERATIONAL PLAN 2023-24
PROGRESS REPORT
Author Executive Officer, Internal Audit & Corporate Performance, Debra Iezzi
CEO's Office | Office of the CEO & Mayor
Index ECM / Subject / 27.04 Corporate Planning
ECM / Subject / 27.07 Council Meetings
Attachments 1. Attachment 1 - Annual Progress Report to 30 June 2024, incorporating
the Q4 progress Report (1 April to 30 June 2024)
2. Attachment 2 - Q4 Operational Plan Progress Report-KPI Graphs Final
3. Attachment 3 - Draft Corporate Plan Performance Measures
EXECUTIVE SUMMARY
This report provides an overview of our performance during the 2023-24 financial year. It expands
on previous quarterly reporting against the 2023-24 Operational Plan to provide an overall synopsis
of the year’s achievements by:
• Identifying factors in our operating environment which have provided both opportunities and
challenges.
• Outlining several key initiatives which are examples of the great outcomes which have been
achieved for the community through the dedication of our staff and the direction of the elected
members.
• Reviewing the progress of all initiatives within the Operational Plan to 30 June 2024 aligned
to the themes of the new Corporate Plan 2023-28.
• Reviewing performance measures within the Corporate Plan and those regularly reported to
Council at an operational level as part of the quarterly reporting cycle.
RECOMMENDATION
That Council note the report by the Chief Executive Officer to the General Committee dated 12
August 2024 regarding the Annual Performance Report and:
A. Note the progress report outlining Council's performance over 2023-24 financial year and
detailing the status of initiatives in the 2023-24 Operational Plan to 30 June 2024 provided
as Attachment 1; and
B. Note the status of Council's Key Performance Indicators as provided as Attachment 2.
C. Note the development of indicators which support the Corporate Plan performance measures
as provided as Attachment 3.
REPORT
In accordance with Sections 166, 174 and 109 of the Local Government Regulation 2012 the Chief
Executive Officer is required to provide an assessment of Council’s progress towards implementing
the Operational Plan at regular intervals of not more than 3 months and to provide an assessment
of Council’s progress towards implementing the Corporate Plan and Operational Plan for inclusion
in the Annual Report.
Our Noosa Council Corporate Plan is the Council’s strategic plan providing overarching direction for
the Council to deliver a sustainable future for Noosa from 2023-2028. The Corporate Plan which is
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
GENERAL COMMITTEE MEETING 12 AUGUST 2024
structured under the five themes of Environment, Liveability, Prosperity, Future and Excellence
guides the annual operational planning process, budget, and the work of all our staff to ensure
resources are allocated to implement the Plan.
The Council’s success in achieving its vision for the future of the Noosa Shire is measured against
65 performance measures which help us to track our progress in achieving our objectives and
desired outcomes. A review of these measures has been undertaken and supporting indicators
developed to assist us in measuring our performance.
The Corporate Plan is achieved through successive Operational Plans and the delivery of more than
38 services to the community. Progress in implementing the Operational Plan is reported quarterly
to Council. This report provides an update on the progress of all initiatives to 30 June 2024
incorporating the Q4 report the period 1/4/24-30/6/24.
1. Our Operating Environment
Over the last year we have been impacted by a number of factors in our operating environment
which provide both opportunities and challenges. Despite this we have continued to deliver quality
services to the community and successfully delivered or progressed a large number of initiatives.
These factors include:
• The Local Government Elections conducted on 16 March 2024 and the deferment of some
decisions until the commencement of the new Council which has affected the progress of
some major initiatives.
• A ‘hot’ construction sector with high growth (approx. 9% in 2023) and characterized by
labour shortages, material supply constraints and high construction costs.
• Cost increases across a range of infrastructure and services as measured by the Council
Cost Index (CCI). In 2023-24 the CCI was 4.4% on top of a 6.9% increase in the previous
year.
• Council’s success in securing substantial grant funding of $14.7M (Operating and Capital
Grants) as well as $127M (QRA Disaster Recovery from 20/22 flood event) which
expanded the capital program and increased pressure on project management services.
• Community expectations with an increased focus on community consultation and
engagement.
• Recruitment challenges with it taking longer to recruit to key positions.
• High employee turnover and a competitive labour market.
• An ambitious Corporate Plan in addition to the implementation of various key strategies and
plans.
• Organisational change with amendments to the organisational structure and transitional
leadership arrangements.
• Competing priorities and resourcing constraints which have impacted the delivery of some
initiatives and increased pressure on service areas.
In response to these factors, we have carefully monitored project planning, reviewed the timelines
of some initiatives and worked to develop our capabilities with a focus on our people, financial
sustainability, our business processes and systems, and our community.
Our People
• Our organisational establishment - the level of staffing resources has increased to support
the delivery of additional services and higher standards of service to the community.
Page 3
GENERAL COMMITTEE MEETING 12 AUGUST 2024
• Our SPARC values (supportive, passionate, authentic, respectful, and committed) - Our
Values in Action Framework outlines the values and behaviours to guide how we interact and
work with each other and the community.
• Focus on employee wellbeing – the Thrive Well Being and Inclusion Program focused on
enhancing mental health and resilience training to enhance the wellbeing and safety of our
employees.
• Learning and development – establishment of a L&D calendar which provides core training
• opportunities to upskill all employees and the introduction of the LEAD leadership
development program linked to corporate priorities incl. the new Corporate Plan, cascading
down to branch plans and individual employee my plans.
• Appointing to key positions – to stabilise operations and achieved through refreshed
recruitment processes, utilizing different recruitment channels, and includes psychometric
testing. A key position being the commencement of the recruitment process for the
permanent CEO role.
• Performance planning – the development of staff performance plans which provide everyone
in the organization with an understanding of their purpose and role, provide the opportunity
to set performance and development goals and increase communication.
Financial Sustainability
• The Council continues to demonstrate prudent and responsible financial management
practices - an independent audit by Queensland Audit Office (QAO) on Council’s 2022/23
financial statements, as adopted with the Annual Report in November 2023, with an
unqualified audit and no additional significant matters raised.
• The Council’s draft 2023/24 financial position is positive, with early indication of balanced
operating results and meeting the required sustainability indicators.
• Looking forward, on 30 June 2024 - Council also adopted a balanced budget for the 2024/25
year.
• The council has attracted significant grant funding - this enabled us to progress flood
restoration works and renew capital infrastructure, supplementing council’s revenue base.
• Improved budget process - especially in relation to the initiation of capital projects (PID
process) for consideration in the budget.
Our business processes and systems
• Noosa 2.0 - continuing to implement business improvements with a focus on ICT capability
and security, improving business processes, and fine tuning the organizational structure.
• Improved business planning - with a focus on enhancing Branch Plans and the review of
Service profiles.
• Improved project management - particularly in the co-ordination of capital projects and
program delivery.
Our community
• A greater focus on community engagement - with the implementation of the community
engagement strategy, providing increased opportunities for the community to have their
say, upskilling staff in community engagement techniques, and taking a more strategic
approach especially when planning for community engagement activities.
• Improving the information flow to our community - especially on matters which directly affect
them and providing increased opportunities to connect with Council.
2. Highlights
Page 4
GENERAL COMMITTEE MEETING 12 AUGUST 2024 The following is a selection of 13 initiatives (from many) that frame the 2023-24 year. Inducting the new Council (Office of the Mayor and CEO) Noosa Council welcomed a new team of Council in April 2024 with a new Mayor, four returning Councillors and two new Councillors. Councillors received the most extensive induction programme ever undertaken by Council over a three month period including but not limited to: Department Briefings, Branch overviews from Development Assessment, Governance, Grants, Waste, Local Laws, Finance, Economical Development, Disaster Management, Environment, Strategy and Sustainability, and Asset Management. Councillors undertook two tours of the Shire visiting facilities and major projects and received induction sessions by external agencies including : Queensland Treasury Corporation, Office of Independent Assessor, LGAQ, Department of State Development, Infrastructure, Local Government and Planning, Unitywater & Tourism Noosa. During the induction process, Councillors received comprehensive information, regular updates, and participated in team- building sessions. This ensured a strong, well-informed, and cohesive Councillor Cohort, ready to tackle the challenges of their four-year term in office. Deployment of licence plate recognition technology for parking regulation (Development and Regulation) Council has successfully procured, installed and deployed new license plate cognition technology. This cutting-edge solution is integral to our efforts in efficiently managing parking within our Local Government area. Better parking regulation supports businesses who rely on the regular turnover of parking for their customers, and residents and visitors who rely on drivers not overstaying so that everyone gets fair access to our busy precincts. Financially Sustainable Council (Corporate Services) Council’s draft 2023/24 financial position, pending completion of Financial Statements and independent audit, has achieved an operating surplus ICT focus on Cybersecurity and System Enhancements (Corporate Services) The implementation of improved security frameworks, monitoring and policy to mitigate cyber security risks. This was supported by increased investment in technology projects during the year across a range of Council facilities and services, including property & rating systems, waste, corporate reporting, network hardware servers and switches, CCTV, asset and fleet management. Financially Sustainable Council (Corporate Services): Council’s draft 2023/24 financial position, pending completion of Financial Statements and independent audit, has achieved an operating surplus Disaster Reconstruction Program 22/23 (Infrastructure Services) Considerable progress has been made on repair and reconstruction of 31 landslides and 15 stormwater culverts and drains impacted by the 2022 rainfall event. Following a lengthy and complex design process, substantial progress has been made on the Black Mountain landslide site in order to stabilise the road and repair convenient access to Cooroy for impacted residents. Other completed sites including stormwater Coles Creek Road, Upper Pinbarren Creek Road, Schriebers Rd, Weyba Esplanade and Golden Gully Road. Reprofiling of the Noosa doggy beach - SEMP (Infrastructure Services) Following initial attempts for a lower “key” dredging program, the project was reprofiled in late 2023 to achieve the full extent of works outlined by Councils Shoreline Erosion Management Plan, and achieve a natural shoreline protection system for the Noosa River estuary and Noosa Sound. This was achieved through redirection of the Noosa River channel and dredging nourishment works to achieve a wide beach, that will be maintained through an ongoing nourishment program. Construction of the new dedicated Disaster Management Centre (Infrastructure Services) A dedicated Local Disaster Co-ordination Centre has been established at Noosa Councils Noosaville
Page 5
GENERAL COMMITTEE MEETING 12 AUGUST 2024 Depot, tapping into Disaster Reconstruction Funding. The centre was created through cost effective re-use of relocated former school buildings and now provides a dedicated co-ordination room and triage facility during disasters, but also can be used continuously throughout the year for disaster preparedness meetings and training. Bridges renewal program (Infrastructure Services) Waste Strategy (Infrastructure Services) Council endorsed Noosa Waste Plan 2023-28 following with extensive input from the community and provides a blueprint to achieve a significant reduction in materials being sent to landfill. The highest source of Council's emissions (63%) is the landfill owned and operated by Noosa Council that receives and manages the Noosa community's residential and commercial waste. The Waste Plan provides a valuable road map to achieve waste diversion target of 61% by 2025. Opening of the Olive Donaldson Pavilion (Community Services) In August 2023 Council was proud to deliver the $1.95M Pavilion facility which will support a number of sports clubs currently based at the complex including Tewantin Noosa Cricket Club, Noosa District Netball Association, and Noosa Beach Classic Car Club, with the opportunity to welcome new sports such as pickleball to the site. This project was proudly funded by the Australian Government, the Queensland Government, Noosa Council and the Australian Cricket Infrastructure Fund. The pavilion will support the current and future demands of the host of clubs who call the complex home, plus address the shortage of toilet facilities. Hinterland Customer service trial – Cooroy Library (Community Services) Council’s customer service team has branched out into the hinterland with the launch of a new satellite help desk at Cooroy Library. The hinterland trial builds on efforts to make Council and its services more convenient to the community in ways that are relevant to individual needs. C ustomer service staff based at the library can help with general Council enquiries, provide advice about Council’s services and facilities as well as receive requests and forms. Kabi Kabi Engagement (Strategy and Environment) Over the last year, Council has been strengthening its historically strong relationship with Noosa’s Traditional Custodians, the Kabi Kabi Peoples. Council held over 28 formal engagements with the Native Title Holders and Directors of the Kabi Kabi Peoples Aboriginal Corporation - the authorised body representing Kabi Kabi Peoples on Native Title and cultural heritage matters. These engagements included workshops and walk on country events to inform our key strategies and plans, as well as site inductions and cultural heritage assessments to inform our infrastructure projects. Of note is the significant engagements held on the Pomona Place Plan, the Destination Management Plan and the Noosaville Foreshore Infrastructure Master Plan; the co-development of the Kabi Kabi Commitment; the support provided on four Kabi Kabi-led projects; and the collaborative workshop with the new Council and Executives. The depth and breadth of engagements held last year has set a strong foundation for Council’s long-term partnership with Kabi Kabi which both improves outcomes and aspirations for Kabi Kabi in the region, as well as enriches culture and liveability in Noosa. Pomona Place Plan (initiation first pilot) (Strategy and Environment) The Pomona Place pilot is a new approach to planning, engaging and improving the liveability of Pomona in partnership with community to ensure it remains a unique and thriving community into the future. A key component of the pilot is to also learn and test new approaches to place based planning that can be applied to other towns and villages across the Shire. The first round of community consultation was undertaken in in August and October in 2023 with over 500 people participating to understand local values , aspirations and ideas about the future to input into the Plan. From this a suit of actions were developed based around key themes that the community were asked to prioritise in the second round of engagement which ran from May through to June 2024 with 300 people participating. The Draft plan is now being prepared based on this community feedback. 3. Noosa Council Operational Plan 2023-24
Page 6
GENERAL COMMITTEE MEETING 12 AUGUST 2024
The annual Operational Plan 2023-24 forms an important part of Council's strategic planning and
sets out the work Council plans to deliver towards the achievement Council's Corporate Plan. The
Operational Plan 2023-24 adopted by Council on 30 June 2023 as part of the budget process was
structured to align with the five Themes and Objectives of the Corporate Plan 2023-28 (i.e.,
Environment, Liveability, Prosperity, Future and Excellence).
The Operational Plan contains 149 initiatives and identifies the activities that deliver business as
usual services to the community which are further detailed in Branch Plans and Service Profiles. An
initiative may relate to broader and long-term efforts aimed at achieving a specific goal or vision (in
this case the initiative may be staged greater than a year) or a specific project with defined objectives
and deliverables.
The format of the Progress Report is to identify those initiatives which are ‘Completed’, ‘On Track’
or experiencing a ‘Minor Disruption’ or ‘Major Disruption’. The majority of initiatives (69%) are either
'complete' 43% or 'on track' 26%, with 17.5% experiencing a 'minor disruption' and 13.5% a 'major
disruption'.
When considering overall progress, it is important to note that factors in our operating environment
have impacted the delivery of some initiatives.
Environment Liveability Prosperity Future
Status Excellence Total
Theme Theme Theme Theme
Complete 20 18 10 6 10 64
On Track 7 9 8 11 4 39
Minor
3 7 2 6 8 26
Disruption
Major
2 7 1 5 5 20
Disruption
Total 32 41 21 28 27 149
The Operational Plan 2023-24 Q4 Progress Report Attachment 1 provides an update on the status
of all initiatives for the quarter and includes a summary of progress for the year. When reviewing
the progress of initiatives, the following should be considered:
• The 23/24 Operational Plan was aligned to the new Noosa Council Corporate Plan, which is
very ambitious and includes initiatives related to the delivery of other key strategies and
plans.
• There are a number of initiatives which are nearing completion which will be finalised in early
24/25 or during the year (particularly those within the ‘on track’ and ‘minor disruption’
categories).
• Initiatives which are ‘on track’ or experiencing ‘minor’ or ‘major’ disruptions have been
reassessed and will be delivered either through relisting them in the new 24/25 Operational
Plan or our business-as-usual service delivery (refer to notations against particular initiatives
in Attachment 1).
• Going forward the opportunity exists to review and better define some project scopes, give
greater consideration to project timeframes or the staging of projects, and Council’s
resourcing capacity.
Page 7
GENERAL COMMITTEE MEETING 12 AUGUST 2024
4. Operational Performance Measures
When reporting progress against the Operational Plan each quarter we have routinely included
performance against 14 operational indicators. The intent is to review these indicators as part of the
review of the development of a Performance Measurement Framework and the implementation of a
new Corporate Performance Reporting System which are initiatives in the 2024-25 Operational Plan.
Once Key Performance Measures are finalised they will be reported to the Council for endorsement
and included in future quarterly reports. In the meantime, we will continue to report progress against
the 14 key performance indicators as previously reported, refer Attachment 2.
While the focus of the review of performance measures has been to further refine those within the
Corporate Plan, a review of Service Profiles for all council services has recently been undertaken
which includes the identification of efficiency and effectiveness performance measures for each
service. Effectiveness measures monitor the progress of objectives, and the outcomes council wants
its services to achieve while efficiency measures monitor the cost of delivering the service. The
Service Profiles were reported to the Council in the 2024-25 Budget process and will continue to be
refined.
5. Corporate Plan Performance Measures
The Noosa Council Corporate Plan 2023-28 identifies 65 Performance Measures under the 5
Themes of the Corporate Plan. These measures have been reviewed by the Executive Team and
as a result further supporting indicators have been identified which will assist us in tracking
performance, refer Attachment 3.
The proposed supporting indicators still require further refinement and will be monitored for future
reporting as we develop our performance measurement framework and implement the Corporate
Performance Reporting System.
Link to Corporate Plan
Theme No. 5 - Excellence
This theme focuses on customer experience, financial sustainability, innovation and technology,
levels of service, governance, our employees and volunteers, funding streams and asset
management practices.
Objective 5.3 - Provide robust and transparent governance systems to build and strengthen
community trust, supported by the implementation of an enterprise risk and opportunity management
framework.
Previous Council Consideration
Ordinary Meeting Minutes - 13 May 2024, Item 6.1
That Council note the report by the Chief Executive Officer (Acting) to the General Committee dated
13 May 2024 regarding the 2023-24 Operational Plan and:
1. Note the progress report for Q3 2023-24 Operational Plan to 31 March 2024 provided as
Attachment 1;
2. Note the comments on the progress of all initiatives identified provided as Attachment 2; and
3. Note the status of Council's Key Performance Indicators as provided as Attachment 3.
Finance
The Operational Plan was approved with the annual Budget on 30 June 2023.
Page 8
GENERAL COMMITTEE MEETING 12 AUGUST 2024
Risk & Opportunities
A failure to achieve the outcomes set out in the Operational Plan would be problematic. In some
cases, projects may take longer than anticipated to achieve the best outcome. Potential risks include:
• The ambitious priorities within the new Noosa Council Corporate Plan 2023-28 which
informed the development of the 2023-24 Operational Plan.
• The organisation's capacity to deliver the 2023-24 Operational Plan particularly given
competing priorities, skill shortages and market conditions and the flow on effects to service
delivery.
• Initiative/Project outcomes may not be realised.
• The development of the Performance Management Framework and the implementation of a
new Corporate Performance Reporting System will assist in monitoring our performance and
support improved decision making.
• The development of a Capability Plan is incorporated in the Corporate Plan 2023-28. This
Plan will consider Council's capacity including systems, finances and workforce
requirements.
Consultation
External Consultation - Community & Stakeholder
Nil
Internal Consultation
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors x Director x Director
x Chief Executive Officer x Community Development x Financial Services
x Executive Officers x Sport & Active Lifestyles x Fleet
x Community Engagement x Arts & Culture x Revenue Services
x People & Culture x Community Connection x ICT
Governance x x Customer Experience x Procurement
Commercial Property
Strategy & Environment Development & Regulation Infrastructure Services
x Director x Director x Director
x Strategic Land Use Planning x Development Assessment x Infrastructure Planning,
Design and Delivery
x Economic Development & Local Laws x Civil and Asset operations
Destination Management
x Environmental Services x Environmental Health x Waste
x Innovation & Digital Hub Building & Plumbing Building & Facilities
Property / Permits x Disaster Management x