Synergy Property Partners- Noosaville- Town Planning Report_REVA
Attached to the e-mail MCU15/0095 & REC15/0022 IDAS Forms, Report & Plans (1 of 3).
TfA Project Group Pty Ltd Synergy Property Partners- Noosaville- Town Planning Report
4.1.1. State Interest—Natural hazards, risk and resilience
The Interim development assessment requirements, for the flood hazard overlay area and the potential bushfire impact
buffer area, are applicable to the proposed development. The table below demonstrates compliance against the
applicable requirements.
Table 3: State interest—Natural hazards, risk and resilience requirements
Requirement Response
For all natural hazards: Development:
Avoids natural hazard areas or mitigates the risks of the The proposed development will not adversely impact on
natural hazard to an acceptable or tolerable level, and or increase any risks to the natural hazard area.
Supports, and does not unduly burden, disaster It is considered to be a small scale development which
management response or recovery capacity and highly unlikely to burden any disaster management
capabilities, and response.
Directly, indirectly and cumulatively avoids an increase in The proposed development will not add to the severity
the severity of the natural hazard and the potential for of potential damage to the natural hazard area on the
damage on the site or to other properties, and site or adjoining properties.
Avoids risks to public safety and the environment from The proposed development will provide for an oily-
the location of hazardous materials and the release of water treatment system for all stormwater captured over
these materials as a result of a natural hazard, and the refuelling / fuel unloading areas to ensure the
release of materials as a result of natural hazards are
mitigated.
Maintains or enhances natural processes and the The proposed development will have no adverse impact
protective function of landforms and vegetation that can on natural landforms.
mitigate risks associated with the natural hazard
4.2. Referral Agencies
Schedule 7 of the Sustainable Planning Regulation, 2009 (the Regulation) lists all potentially relevant referral
triggers and their jurisdictions. The table below provides an extract from Schedule 7 and identifies those
referral triggers considered relevant to the proposed development. The State Assessment Referral Agency
(SARA) will be the central point of contact for all referrals.
Table 4: Extract table from Schedule 7 of Sustainable Planning Regulations 2009
Application Involving Comment on Referral Trigger
Schedule 7, TABLE2 - Development made assessable under a planning scheme, temporary local planning instrument,
preliminary approval to which section 242 of the Act applies or State planning regulatory provisions
Page 13 of 30 6/10/2015
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.