SUPERSEDED - Decision Notice OPW22 0241 [As Published]
Driveway Plan as submitted to
Council on 15 December 2022
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 13 January 2025, unless an application to extend the currency period
is approved by Council.
SITE SPECIFIC CONDITIONS
3. The existing tree in the road reserve adjacent to the proposed driveway must be wholly
removed as part of these works
PRIOR TO COMMENCEMENT OF WORKS
Engineering
4. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
5. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
6. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
7. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Other relevant parties
8. A Construction Management Plan must be submitted at least 5 working days prior to prestart
meeting and must address the following:
a. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD)
b. provision for safe pedestrian and vehicle access across the frontage of the site both
during daily construction and after daily construction has ceased.
9. Any changes to the details associated with the Principal Contractor during construction, must
be notified to council in writing within five business days of the change occurring.
10. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
11. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
Page 2 of 7
Document Set ID: 22243197
Version: 2, Version Date: 18/01/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.