19915 Traffic Engineering Report
Good Shepherd Lutheran College, Noosaville
March 2023
Table 5 – Car Parking Demand Survey Results 2022
Parking Available @ 8:30 AM Peak @ 3:00 PM Peak
Zone Spaces Spaces Utilisation Spaces Utilisation
Area Occupied % Occupied %
A 15 10 67% 12 80%
B 42 21 50% 48 114%
C 0 (Area Removed) 0 0
D 47 30 64% 49 104%
E 153 134 88% 132 86%
TOTAL 255 195 241
(excludes 2 motorcycle bays,
drop off zone)
# where utilization exceed 100%, cars were standing illegally or waiting in aisles
Results indicate that the overall car parking demand is very similar in 2020 and 2022,
with consistent demand for the College.
A summary of parking demand on the College for all Areas (excluding Pre‐prep) is
provided in Figure 6 and clearly shows the peak demand occurring at 8:30am and
3:00pm in both 2020 and 2022. Whilst there is no change to the peak demand. Survey
data suggests there are more vehicles parked on site in 2022, which is due to the
additional number of secure staff parking spaces available in the new car park.
Figure 6 – Parking Occupancy for all Parking Areas (Excluding Pre‐Prep)
Car Parking Occupancy
300
250
Number of Cars Parked
200
150
100
50
0
Time of Day
Series2 Series3
Page 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Traffic Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.