Decision Notice - Minor Change - OPW19 0203 03 [As Published] · OPW19/0203.03

of 13

Text shows just the words. Original shows the document exactly as it was published.

                              i.       contact details for the on-site manager;
                              ii.      dispute resolution procedures.
               10.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               11.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               12.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               13.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               14.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use approval
                              132007.738 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines;
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Roadworks
               15.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.
               16.    The installation and/or modification of any traffic signs, street signs, line marking and Raised
                      Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
                      Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
                      installation system. All new signage must be Class 1 retroreflective material in accordance
                      with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
                      1: Retroreflective sheeting.
               17.    The developer must notify Council’s Traffic Engineer for any works involving the removal or
                      modification of existing council traffic signs and/or parking bays prior to such works
                      commencing.
               18.    Root barriers are required to be installed behind the back of kerb for all new kerbs within 5m
                      of a trunk of a tree.
                      Pavement Design and Construction
               19.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.


                                                                                                         Page 4 of 13
Document Set ID: 22809336
Version: 4, Version Date: 13/02/2024

Used in these records

About this file

File size
185 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - OPW19 0203 03 [As Published].pdf · 185 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.