Skip to the record
The only place to find full transcripts.

Council archive · source document

Attachment 14- Amended Traffic Impact Assessment Report MCU12/0208

of 204

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                 Noosa on Weyba
                                         Revised Traffic Impact Assessment as Response to Council’s Request for Further Information



3.3            Proposed Access Strategy
3.3.1          Holistic Report Outcomes Discussion

3.3.1.1        Preferred Traffic and Transport Option
From a traffic and transport perspective the optimum access strategy was found to be a tie between options
5A and 6A. These options shared the following elements to their access strategies:
        > Roundabout access to Walter Hay Drive
        > Road access to Tidswell Road
        > Underpass connecting the east and west of the development under Walter Hay Drive.
However, due to engineering costs and ecological constraints the Walter Hay Drive underpass was not
considered viable by the design team.

3.3.1.2        Best Holistic Scoring Option
The design option that was considered best from an overall (Transport + Ecological + Civil) scoring
perspective was Option 4. This was not the highest performing from a Transport perspective, but considered
the best when considering the environment. The key design elements of this strategy are as follows:
        > Roundabout access to Walter Hay Drive
        > No access to Tidswell Road
        > No underpass connecting the east and west of the development under Walter Hay Drive.
This option was rejected on traffic and transport grounds for the following reasons:
        > The inability of the option to deliver any sort of meaningful public transport accessibility
        > The lack of connectivity between Noosa on Weyba and the Weyba Downs Development to the
          south
        > The lack of active travel connectivity to the south of the development.

3.3.1.3        Design Masterplan Option
Given the issues with the options highlighted above it was considered that the option which scored best but
did not have any major design flaws was Option 6. This option had the following access elements:
        > Roundabout access to Walter Hay Drive
        > Road access to Tidswell Road
        > No underpass connecting the east and west of the development under Walter Hay Drive.




510119                                                        Cardno                                              September 2013
Prepared for Northbrook Corporation Pty Ltd                                                                             Page 24

Used in these records

About this file

File size
7.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 14- Amended Traffic Impact Assessment Report MCU12_0208.pdf · 7.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.