Attachment 14- Amended Traffic Impact Assessment Report MCU12/0208

of 204

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                 Noosa on Weyba
                                         Revised Traffic Impact Assessment as Response to Council’s Request for Further Information



Figure 4-2 Active Transport Strategy




The preliminary pedestrian and cyclist network proposed on the Vee Design Map 1.7 Open Space, Road and
Mobility (Pedestrian and Cycle) indicates that there will be extensive off road paths catering to pedestrian
desire lines connecting residents to the local collector roads and between the two sides of the development.
As for paths leading to external areas, the proposed network provides connections east to Lake Weyba,
south along Tidswell Road and west along Hollett Road towards Eumundi-Noosa Road.
These pedestrian pathways are considered appropriate for an urban standard and where off road cycle
facilities are proposed to extend through the development, along collector streets where higher traffic
volumes are expected, will be shared paths. On road cycling will be permitted for the lower order streets,
where it is expected that traffic volumes will be sufficiently low to allow for the road to be shared between
vehicles, cyclists and pedestrians.

4.3            Cross Sections
Where sufficient area is available, the SCRC typical cross-sections have been utilised. In areas of ecological
sensitivity, modified typical sections have been utilised to reduce the extent of clearing as the conservation of
existing green space is considered the priority where possible. The road types utilised and the location of
these road types is outlined in more detail within the Noosa on Weyba Engineering Report, which was
produced by Cardno.
As such, in accordance with the Road Planning and Design Manual (RPDM), the desirable lane width for bus
carrying routes is 3.7m which provides 7.4m wide carriageways in addition to 1m wide cycle lanes. Where
not constrained by conservation areas, this width has been ensured for the collector roads where the bus
service diversion has been proposed.




510119                                                        Cardno                                              September 2013
Prepared for Northbrook Corporation Pty Ltd                                                                             Page 27

Used in these records

About this file

File size
7.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 14- Amended Traffic Impact Assessment Report MCU12_0208.pdf · 7.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.