Decision Notice - MCU22 0171 [As Published] · MCU22/0171

of 8

Text shows just the words. Original shows the document exactly as it was published.

                                                                                Officer:            Lisa Pienaar
                                                                                Direct Telephone:   07 5329 6514
                                                                                Our Reference:      MCU22/0171
                                                                                Your Reference:     PR22001

               17 April 2023


               CE Cullen & M Cullen
               C/- Mallee Group Pty Ltd
               4 Lalwinya Street
               BUDDINA QLD 4575
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 14 April 2023, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.       APPLICATION DETAILS

                   Application No:              MCU22/0171

                   Street address:              128 Gympie Tce Noosaville Qld 4566

                   Real property description:   Lot 1 MCH 3881

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.       DECISION DETAILS

               Council decided to issue the following type of approval:
               •        Development Permit for Material Change of Use - Dual Occupancy
               3.       CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.       ASSESSMENT MANAGER CONDITIONS

               PLANNING
                        When Conditions must be Complied With
                   1.    Unless otherwise stated, all conditions of this Decision Notice must be complied with prior
                         to the use commencing, and then compliance maintained at all times while the use
                         continues.




               ABN 97.969.214.121                                                                PO Box 141
               noosa.qld.gov.au                                                           Tewantin QLD 4565
               [email protected]                                                           07 5329 6500
                                                                                                           Page 1 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023
Full text of the other 7 pages

Page 2

                      Approved Plans
                 2.     Development authorised by this approval must be undertaken generally in accordance with
                        the Approved Plans listed in the tables below. The plans must be amended to incorporate
                        the amendments listed within the table below and resubmitted to Council prior to the issue
                        of any Development Permit for Operational Works.

                         Plan          Rev. Plan/Document Name                                    Date
                         No.

                         DD1.2         -      Basement     Floorplan,    prepared   by    Sparkes 24.03.2023
                                              Architects

                         DD1.6         -      Landscaping Areas, prepared by Sparkes Architects   24.03.2023

                         DD2.1         -      North Elevation, prepared by Sparkes Architects     24.03.2023

                         DD3.2         -      Section B, prepared by Sparkes Architects           24.03.2023

                         DD4.2         -      Indicative materials and details                    14/02/2023

                      The following plans require amendment.

                         Plan          Rev.   Plan/Document Name                                   Date
                         No.

                         DD1.1         -      Site Plan, prepared by Sparkes Architects            24.03.2023

                         DD1.3         -      Ground Floorplan, prepared by Sparkes Architects     24.03.2023

                         DD1.4         -      Driveway, prepared by Sparkes Architects             24.03.2023

                         DD1.5         -      First Floorplan, prepared by Sparkes Architects      24.03.2023

                         DD2.2         -      East Elevation, prepared by Sparkes Architects       24.03.2023

                         DD2.3         -      South Elevation, prepared by Sparkes Architects      24.03.2023


                         DD2.4         -      West Elevation, prepared by Sparkes Architects       24.03.2023

                         DD3.1         -      Section A, prepared by Sparkes Architects            24.03.2023

                         DD3.3         -      Section C, prepared by Sparkes Architects            24.03.2023

                         Amendments           Remove the shade sails located within the Gympie Terrace front 6.0
                                              metre setback


                      Currency Period
                 3.     This development approval lapses if the use has not happened by 14 April 2029, unless
                        an application to extend the currency period is approved by Council.
                      Building Height
                 4.     The maximum height of the development must not exceed that shown on the approved
                        plans.




                                                                                                         Page 2 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 3

                 5.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld)
                        which certifies that the building does not exceed the maximum height requirement of this
                        Decision Notice.
                       Performance Bond
                 6.     Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must
                        be submitted to Council, to secure performance of all conditions of this approval, prior to
                        the issue of a Development Permit for Operational Works. The cash bond or trading bank
                        guarantee will be returned on performance of the conditions of approval less any costs
                        incurred by Council in respect of enforcing performance of this permit. Council reserves the
                        right to call upon the bond or guaranteed sum to effect compliance with conditions.
                       Building Appearance
                 7.     External finishes of the building must be a mix of lightweight and textured external finishes,
                        with masonry areas incorporating a variety of textured finishes to break up the surface.
                 8.     The external Outrigger/Sun-shades as detailed on the proposed plans are to be maintained
                        for the life of the building. The Outrigger/ Sun-shades are to have a maximum of 50%
                        openings.
                 9.     The sun- shades located within the rear 6.0 metre setback to Chaplin Park are to be of a
                        light weight and open construction.
                 10.    All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
                        the like thus remaining as open structures.
                 11.    All balustrades to decks and balcony areas must be open or transparent.
                 12.    External colours and finishes must be of an understated colour scheme and low-reflective
                        roofing and cladding materials.
                 13.    All air conditioning units or other mechanical equipment must be fully enclosed or screened
                        such that they are not visible from the street frontages nor adjoining properties.
                 14.    Waste storage areas, clothes drying areas and external storage areas must be screened
                        from view of the street.
                       Fencing and Walls
                 15.    Any street fencing must not exceed 1.8 metres in height, be set back an average of 1 metre
                        and articulated to provide visual interest by stepping the design.
                 16.    The area of land between the fence and the front property boundary must be densely
                        landscaped to screen any fencing from the street.
                 17.    The proposed fill and side boundary fences must taper down to the rear and front boundary
                        to the reasonable satisfaction of the Manager Development Assessment.
                 18.    The rear gate must at least 50% visually permeable to enable landscaping behind to be
                        visually dominant where viewed externally.
                 19.    The wall on the western side boundary at the rear (adjacent to the stairs) must step down
                        from the gate to the rear (northern) boundary, with the fence height no greater than 2 metres
                        high from existing ground level for a length of 3 metres in from the rear (northern) boundary.
                        The fence is to maintain privacy to the adjoining site to the west.
                       Protection of Privacy
                 20.    The upper level terrace must include either balcony planter boxes, balustrading or fixed
                        external screens, positioned in such a way to obscure direct views into the private open
                        space areas of the adjoining property to the north as shown on the Approved Plans.




                                                                                                        Page 3 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 4

                       Landscaping
                 21.    The development site must be landscaped. The works must be undertaken in accordance
                        with an Operational Works approval and the Noosa Plan for that specific area and must
                        include in particular:
                        a.    Detailed landscape plans undertaken by a qualified person generally in accordance
                              with the works shown on the Approved Plans;
                        b.    Landscape screening in the form of large trees provided to the eastern and western
                              boundary capable of growing 8-10 metres in height at maturity;
                        c.    vegetation with vertical scale to be provide screening / softening of the Southern
                              elevation from Gympie Terrace, designed such that 30% of the eastern elevation will
                              be softened at maturity;
                        d.    removal or reduction in size of rainwater collection tanks from the front landscape
                              garden adjacent Gympie Terrace to ensure deep planting is achievable.
                 22.    All landscape works must be established and maintained in accordance with the approved
                        design for the life of the development, and in a manner that ensures healthy, sustained and
                        vigorous plant growth. All plant material must be allowed to grow to full form and be
                        refurbished when its life expectancy is reached.
                 23.    All landscape works must be maintained generally in accordance with the approved design
                        for the life of the development.
                       Waste Management
                 24.    A waste storage area must be provided in accordance with Planning Scheme Policy 9,
                        Waste Management and the Noosa Plan’s Waste Management Code, including an external
                        imperviously paved area correctly sized for all refuse and recycling containers and suitably
                        screened from public places and neighbouring properties.
                       Community Management Statement
                 25.    Any proposed Community Management Statement required for the development pursuant
                        to the Body Corporate and Community Management Act 1997 must be submitted to Council
                        for endorsement at the same time as submission of the Building Format Plan (or similar) to
                        Council for compliance assessment.
                 26.    All clauses and by-laws of the proposed Community Management Statement must accord
                        with the requirements of this Decision Notice and, in particular, must include the following
                        additional clause:
                              The dwelling units are not permitted to be used for short term accommodation, unless
                              where identified as accepted development by the Noosa Plan or where there is a
                              Development Permit for Material Change of Use for Short Term Accommodation in
                              effect. Short term accommodation means the use of the premises for providing
                              accommodation of less than 3 consecutive months to tourists or travellers.
                       External Works
                 27.    Gympie Terrace must be upgraded for the length of its frontage to the subject site. The
                        works must be undertaken in accordance with an Operational Works approval, be generally
                        accordance with DME Project’s Proposed Layout Ground Floor (Revision C) dated March
                        2023 and must include the construction of a pedestrian footpath in accordance with the
                        conditions of this Decision Notice.
                 28.    A footpath must be provided for the development. The works must be undertaken in
                        accordance with an Operational Works approval and must include in particular:
                        a.    A 2 metre wide concrete footpath within the road verge for the entire length of the site’s
                              frontage to Gympie Terrace.
                        a.    The new pathway must be constructed of materials similar in colour and finish to the
                              existing pathway between the subject site and Mill Street.


                                                                                                          Page 4 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 5

                       Property Access and Driveways
                 29.    Vehicle access to 128 Gympie Terrace is limited to the existing access easement via Mill
                        Street and must be constructed generally in accordance with DME Project’s Proposed
                        Layout Driveway and Basement (Revision C) dated March 2023.
                       Car Parking
                 30.    A minimum of 5 car parking spaces must be provided and marked on the site. The works
                        must be undertaken in accordance with an Operational Works approval and must include
                        in particular dimensions, crossfalls and gradients in accordance with Australian Standard
                        AS2890: Parking Facilities.
                       Stormwater Drainage
                 31.    The site must be provided with a stormwater drainage system connecting to a lawful point
                        of discharge. The works must be undertaken in accordance with an Operational Works
                        approval and be generally in accordance with DME Project’s Stormwater Details (Revision
                        C) dated March 2023.
                 32.    A site-specific Dewatering and Acid Sulfate Management Plan must be submitted and
                        accepted by Council prior to the issue of an Operational Works permit. The site-specific
                        Dewatering and Acid Sulfate Management Plan must be prepared by a suitably qualified
                        person and demonstrate how Acid Sulfate affected water encountered during excavation
                        will be treated and disposed of.
                 33.    A clause must be included in any future Community Management Statement that states:
                        a.    the ongoing maintenance of the basement sump is wholly the responsibility of the
                              property owner(s).
                       Services
                 34.    Unless otherwise stipulated by telecommunications legislation at the time of construction,
                        the development must be provided with all necessary conduits, pits and pipes to
                        accommodate the future connection of optic fibre technology telecommunications.
                 35.    Certification must be submitted to Council from all relevant service providers (Energex,
                        NBN and Unitywater) which certifies that the development has met the requirements of this
                        Decision Notice and all applicable legislation at the time of construction.
                       Easements
                 36.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                        infrastructure located on the subject site must be placed within an easement registered
                        against the title of the property.
                 37.    All easements must be designed in accordance with the planning scheme and granted at
                        no cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                        documentation must be in accordance with the Grantee’s standard easement terms. Draft
                        easement documentation must be submitted to Council for endorsement.
                 38.    All works must be kept clear of any existing or proposed easements on the subject land,
                        unless agreed otherwise in writing by the Grantee.
                       Geotechnical Stability
                 39.    All works must be carried out in accordance with a Geotechnical Report (or part thereof)
                        prepared by a qualified person* and endorsed through an Operational Works approval.
                       *(Refer to Advisory Note)
                       Earthworks and Retaining Walls
                 40.    All fill and associated batters must be undertaken in accordance with an Operational Works
                        approval, contained entirely within the subject site unless written permission from the
                        respective landowner(s) is provided to Council and be generally in accordance with DME
                        Project’s Earthworks Sections 1 and 2 (Revision B and C, respectively) dated March 2023.


                                                                                                        Page 5 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 6

                 41.    All retaining walls must be designed and constructed in accordance with the planning
                        scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
                        walls that are publicly accessible and exceed 1.0m in height must be fitted with a
                        commercial grade safety fence.
               5.      REFERRAL AGENCIES

               Not applicable.
               6.      ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                       Building and Construction Industry (Portable Long Service Leave) Levy
                 42.    The QLeave levy must be paid prior to the issue of a development permit where it is
                        required. Council will not be able to issue a Decision Notice without receipt of details that
                        the Levy has been paid.
                       Co-ordination of Operational Works Assessment
                 43.    Additional application fees apply to Operational Work applications where the different
                        aspects of the works are lodged separately. Significant savings in application fees will result
                        if all works are lodged in a single application.
                       Qualified Person
                 44.    For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                        for the development, a qualified person is considered to be a person who:
                        a.    is a Registered Professional Engineer of Queensland (RPEQ); and
                        b.    has a degree in civil engineering or engineering geology; and
                        c.    has a minimum of 5 years experience in the field of geotechnical engineering or
                              engineering geology.
                 45.    For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                        landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                        current experience in the field of landscape design.
                        Infrastructure Charges
                 46.    All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                        made pursuant to the planning legislation and regulations current at the time of issue. For
                        further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                        development/development-tools-guidelines/infrastructure-charges
               7.      PROPERTY NOTES

               Not applicable.
               8.      VARIATION APPROVAL DETAILS

               Not applicable.
               9.      FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required               Subject of the required Development Permit

                Development Permit for Operational Works          Access and Frontage works, Stormwater,
                                                                  Drainage work, Earthworks, Landscaping.

                Development Permit for Building Works             All building work.




                                                                                                         Page 6 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 7

               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               12.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               for Lisa Pienaar
               Development Planner



               Enc:   Appeal Rights
                      Infrastructure Charge Notice
                      Approved Plans/Documents
               cc.    Unitywater




                                                                                                       Page 7 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Page 8

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 8 of 8
Document Set ID: 22375366
Version: 3, Version Date: 19/04/2023

Used in these records

About this file

File size
159 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - MCU22 0171 [As Published].pdf · 159 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.