Council Decision - Minor Change - 51994 1249 03 [As Published]
23. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
24. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
Damage to infrastructure
25. Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
26. Where damage occurs to any Council asset as a result of the landscaping works, the damage
must be repaired immediately where it creates a hazard that presents risk to person or
property. Non-hazardous damage must be repaired prior to completion of works.
Car Parking
27. The applicant must comply with the requirements of any Infrastructure Agreement entered
into with the Council with respect to the payment of car parking contributions in relation to
the proposed development. In the event that the Infrastructure Agreement does not apply a
minimum of 42car parking space must be provided and marked on the site and made
available and accessible at all times while the use is open for business.
28. A minimum of 38 car parking spaces must be provided on the site in accordance with
approved plans; made available and accessible at all times while the use is open for
business.
29. The new (or modified) car parking spaces must comply with AS/NZS2890.1:2004 Parking
Facilities -Part 1: Off-street car parking.
30. All car parking areas and access driveway must be maintained exclusively for vehicle parking
and manoeuvring and kept in a tidy and safe condition at all times.
31. Certification by a suitably qualified person for the new (or modified) car parking spaces is to
be submitted to Council upon the completion of works and prior to issuing the Certificate of
Classification to confirm compliance with the conditions of this permit.
Additional conditions (numbering to follow conditions of each relevant approval)
Performance Bond
32. Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
will be returned on performance of the conditions of approval less any costs incurred by
Council in respect of enforcing performance of this permit. Council reserves the right to call
upon the bond or guaranteed sum to effect compliance with conditions.
Nature and Extent of Approved Use
33. No structures are approved or permitted within the Park Road or Hastings Street road
reserve.
Landscaping
34. The development site must be landscaped. The works must be undertaken in accordance
with an Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. the works shown on the approved concept plan & sections
b. landscape gardens along the Hastings Street and Park Road frontages adjacent
tenancy 3,4 and 5 to incorporate the use of structural soil cells to create suitable volume
of growing media capable of sustaining tree growth
Page 7 of 10
Document Set ID: 22821200
Version: 5, Version Date: 23/02/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original