SUPERSEDED Decision Letter - Change to an Existing Approval - 010.2003.00221157.002 [As Published] · 132003.221157.2
2003/221157
6.4. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
6.5. The disposal method for clearing works is to be submitted in conjunction with an
application for a Development Permit for Operational Work. The Applicant is advised
that other methods may be considered provided full details of the method are
submitted.
6.6. The Applicant is advised that burning off is an unacceptable method of disposal.
7. The northeastern wall of the building is to incorporate a mixture of materials including timber
boards and pre-cast concrete wall panel.
8. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
9. Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like,
thus remaining as open structures.
10. The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
Dishwashers and washing machines are excluded from this requirement.
11. Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for operational works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
12. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
13. The Development Permit for a material change of use of premises lapses if the use has not
happened by 30 June 2013, unless an application to extend the currency is approved by
Council.
14. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
Building Services
15. An identification survey of the subject site is to be carried out by a Licensed Surveyor and is to
be submitted to Council at the time of foundation inspection or immediately thereafter. Such
survey shall set out the boundaries of the site and the position of the buildings on the site.
16. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of the work confirming compliance with the
maximum building height above natural surface, required by the provisions of the Planning
Scheme.
17. The plans submitted for a Development Permit for building works on each allotment are to
comply with the following: -
17.1. The maximum height of each garage within 0.75 metres of the applicable side
boundary shall not exceed 4.5 metres.
17.2. The mean height as above shall not exceed 3.5 metres.
Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Letter - Change to an Existing Approval - 010.2003.00221157.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 71 KB (small file)
- File type
No other editions are linked here.