Minor Change Existing Approval - MCU22 0196 01 & OPW22 0295 01 (As Published) · MCU22/0196.01

of 16

Text shows just the words. Original shows the document exactly as it was published.

                                                                                       Officer:          Mathew Pinese
                                                                                       Direct Telephone: 07 5329 6245
                                                                                       Our Reference:    MCU22/0196.01
                                                                                                         OPW22/0295.01
                                                                                       Your Reference:   N/A

               22 October 2025


               Looroo Pty Ltd TTE
               C/- Mr NL Francis
               PO Box 1950
               NOOSA HEADS QLD 4567
               [email protected]



               Dear Nathan
                                            Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 20 June 2024, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU22/0196.01 & OPW22/0295.01

                   Street address:              130 – 132 Gympie Terrace, Noosaville Qld 4566

                   Real property description:   Lot 3 on MCH3881

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 10 October 2023.
               •       Development Permit for a Material Change of Use – Multiple Dwelling (4 units)
               •       Development Permit for Operational Works – Landscaping, Stormwater & Earthworks.
               In relation to the request to make a minor change to the existing approval, Council on 17 October
               2025, decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change to MCU22/0196.01 and amend condition 3,
               B.      Delete condition 10 as the applicant has provided a lift that enables access for people with
                       limited mobility to upper levels,
               C.      Approve the change to OPW22/0295.01 and amend condition 1,
               D.      Delete condition 10a




               ABN 97.969.214.121                                                              PO Box 141
               noosa.qld.gov.au                                                         Tewantin QLD 4565
               [email protected]                                                         07 5329 6500
                                                                                                       Page 1 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025
Full text of the other 15 pages

Page 2

               3.     CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.     ASSESSMENT MANAGER CONDITIONS

                                       MATERIAL CHANGE OF USE – MCU22/0196.01
               PLANNING
                      When Conditions must be Complied With
               1.     Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                      the use commencing, and then compliance maintained at all times while the use continues.
                      Currency Period
               2.     This development approval lapses if the use has not happened by 27 July 2029, unless an
                      application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the tables below.

                         Plan No.          Rev.    Plan/Document Name                             Date

                        C1.0               -       Basement Floor Plan, prepared by Chris 09-09-25
                                                   Clout Design

                        C1.1               -       Ground Floor Plan, prepared by Chris Clout 09-09-25
                                                   Design

                        C1.2               -       Upper Floor Plan, prepared by Chris Clout 09-09-25
                                                   Design

                        C1.3               -       Roof Plan, prepared by Chris Clout Design      09-09-25

                        C2.0               -       Elevations, prepared by Chris Clout Design     09-09-25

                        C3.0               -       Sections, prepared by Chris Clout Design       09-09-25

                        C3.1               -       Sections, prepared by Chris Clout Design       09-09-25

                      Building Height
               4.     The maximum height of the development must not exceed 8 metres above the natural ground
                      level and the exposed portion of the external façade of the building, except for the apex of
                      the roof of the units which must not exceed 8.535 metres.
               5.     The ground around the basement level is to be backfilled to ensure no part of the basement
                      is above finished ground level.
               6.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that the buildings do not exceed the maximum height requirement of this Decision
                      Notice.




                                                                                                      Page 2 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 3

                      Performance Bond
               7.     Security in the form of a cash bond or trading bank guarantee to the sum of $40,000 must
                      be submitted to Council, to secure performance of all conditions of this approval, prior to the
                      issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
                      will be returned on performance of the conditions of approval less any costs incurred by
                      Council in respect of enforcing performance of this permit. Council reserves the right to call
                      upon the bond or guaranteed sum to effect compliance with conditions.
                      Water & Sewer Connections
               8.     An underground connection to reticulated water and sewerage must be provided to the
                      premises in accordance with the standards and requirements of Northern SEQ Distributor–
                      Retailer Authority (Unitywater).
               9.     A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the premises.
                      Built Form
               10.    Deleted.
                      Building Appearance
               11.    External design features, materials and finishes must be as shown on the Approved Plans,
                      with no inclusions or alterations made without approval in writing by Council.
               12.    External finishes of the building must be a mix of lightweight and textured external finishes,
                      with masonry areas incorporating a variety of textured finishes to break up the surface.
               13.    All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
                      the like thus remaining as open structures.
               14.    All balustrades to decks and balcony areas must be open or transparent.
               15.    External colours and finishes must be of an understated colour scheme and low-reflective
                      roofing and cladding materials.
               16.    All air conditioning units or other mechanical equipment must be fully enclosed or screened
                      such that they are not visible from the street frontages nor adjoining properties.
               17.    Waste storage areas, clothes drying areas and external storage areas must be screened
                      from view of the street.
                      Fencing and Walls
               18.    Any street fencing must not exceed 1.8 metres in height, be set back an average of 1 metre
                      and articulated to provide visual interest by stepping the design. Any fencing on the front
                      boundary must either:
                      a.      not exceed a maximum height of 1.2 metres;
                      b.      be of open construction.
               19.    The area of land between the fence and the front property boundary must be densely
                      landscaped to screen any fencing from the street.




                                                                                                       Page 3 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 4

                      Landscaping Works
               20.    The development site must be landscaped in accordance with the PSP2 – Landscaping. The
                      works must be undertaken in accordance with the Noosa Plan for that specific area and must
                      include in particular:
                      a.      a minimum 2 metre landscape setback on the front boundary, excluding driveway
                              areas;
                      b.      the works generally shown on the approved landscape plan except where varied by
                              the conditions of this approval;
                      c.      planting of shrubs and trees to the site’s frontage that will visually frame and soften the
                              presentation of the built form to the street;
                      d.      provision of screen planting along the side and rear boundaries to protect the privacy
                              of adjoining properties;
               21.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
                      Waste Management
               22.    A waste storage area must be provided in accordance with Planning Scheme Policy 9, Waste
                      Management and the Noosa Plan’s Waste Management Code, including an external
                      imperviously paved area correctly sized for all refuse and recycling containers and suitably
                      screened from public places and neighbouring properties.
                      Community Management Statement
               23.    Any proposed Community Management Statement required for the development pursuant to
                      the Body Corporate and Community Management Act 1997 must be submitted to Council for
                      endorsement at the same time as submission of the Building Format Plan (or similar) to
                      Council for compliance assessment.
               24.    All clauses and by-laws of the proposed Community Management Statement must accord
                      with the requirements of this Decision Notice and, in particular, must include the following
                      additional clauses:
                      a.      The dwelling units are not permitted to be used for short term accommodation, unless
                              where identified as accepted development by the Noosa Plan or where there is a
                              Development Permit for Material Change of Use for Short Term Accommodation in
                              effect. Short term accommodation means the use of the premises for providing
                              accommodation of less than 3 consecutive months to tourists or travellers.
               ENGINEERING
                      Bonds
               25.    A site compliance bond of $50,000 is to be submitted to Council prior to the pre-start meeting.
                      The pre-start meeting will only be held once Council's Construction Engineering Officer has
                      confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               26.    Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works;
                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s; and
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.


                                                                                                          Page 4 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 5

                      External Works
               27.    Gympie Terrace must be upgraded for the length of its frontage to the subject site. The
                      works must be undertaken in accordance with the conditions held within this Decision Notice,
                      and must include in particular:
                      a.      construction of a 2.0-metre-wide pedestrian footpath in accordance with the conditions
                              of this Decision Notice; and
                      b.      removal of the existing property access and reinstatement of the kerb, footpath and
                              verge area to match the balance of the site frontage, including the provision of topsoil
                              and turf where the existing verge is grassed.
                      Site Access and Driveways
               28.    A sealed access driveway must be provided from Gympie Terrace to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      the conditions held within this Decision Notice.
               29.    Access onto Gympie Terrace is limited to ‘left-in, left-out’ only.
                      Car Parking
               30.    A minimum of 9 car parking spaces must be provided on site. The works must be undertaken
                      in accordance with the conditions held within this Decision Notice and must include in
                      particular:
                      a.      1 visitor parking space within the total and are accessible at all times for visitor use;
                      b.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
                      Pedestrian and Bicycle Facilities
               31.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with the conditions held within this Decision Notice and must
                      include in particular a 2.0-metre-wide footpath within the road verge for the entire length of
                      the site’s frontage.
                      Stormwater Drainage
               32.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with the conditions held within this
                      Decision Notice.
                      Services
               33.    Reticulated electricity and telecommunication services must be provided to each unit in
                      accordance with the standards and requirements of the relevant service provider.
               34.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               35.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               36.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               37.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.


                                                                                                           Page 5 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 6

               38.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               39.    All fill and associated batters must be undertaken in accordance with the conditions held
                      within this Decision Notice and be contained entirely within the subject site unless written
                      permission from the respective landowner(s) is provided to Council.
               40.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               41.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.




                                                                                                      Page 6 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 7

                                       OPERATIONAL WORKS – OPW22/0295.01
               APPROVED PLANS
                      Approved Plans
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development.

                        Plan No.          Rev.   Plan/Document Name                        Date

                        32225-OW3.1       B      Earthworks Plan                           6    September
                                                                                           2023
                                                 prepared by SCG Consulting

                        32225-OW3.2       A      Earthworks Sections                       6    September
                                                                                           2023
                                                 prepared by SCG Consulting

                        32225-OW4.1       B      Driveway & Access Plan                    6    September
                                                                                           2023
                                                 prepared by SCG Consulting

                        32225-OW4.2       B      Driveway Levels                           6    September
                                                                                           2023
                                                 prepared by SCG Consulting

                        32225-OW4.3              Driveway Details                          September
                                                                                           2022
                                                 prepared by SCG Consulting

                        32225-OW6.1              Signage Plan                              September
                                                                                           2022
                                                 prepared by SCG Consulting

                        32225-SW1.1       B      Stormwater Management Plan                6    September
                                                                                           2023
                                                 prepared by SCG Consulting

                        32225-SW1.2              Stormwater Details                        September
                                                                                           2022
                                                 prepared by SCG Consulting

                        CD-000            B      Cover Sheet, prepared by, Project Urban   19/09/2023
                                                 As-Con Markup Annotated by Project
                                                 Urban

                        CD-001            A      Specification Notes, prepared by, Project 23/06/2023
                                                 Urban

                        CD-100            B      Basement Floor Plan, prepared by, Project 19/09/2023
                                                 Urban
                                                 As-Con Markup Annotated by Project
                                                 Urban

                        CD-101            C      Ground Floor Plan, prepared by, Project 22/09/2023
                                                 Urban
                                                 As-Con Markup Annotated by Project
                                                 Urban




                                                                                               Page 7 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 8

                        CD-102                    B      Upper Floor Plan, prepared by, Project 22/09/2023
                                                         Urban

                        CD-200                    A      Construction Details, prepared by, Project 23/06/2023
                                                         Urban

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 16 October 2025, unless an application to extend the currency period
                      is approved by Council.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               4.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               5.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               6.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works; and
                      b.      Other relevant parties
               7.     A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              a.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;
                              b.       Maintenance of safe vehicle and pedestrian access across the frontage of the site
                                       both during daily construction and after daily construction has ceased;
                              c.       Proposed fencing to the site during the construction phase of the development;
                              d.       Adequate parking arrangements for construction workers; and
                              e.       Maintenance and protection of water quality and existing drainage lines through
                                       the construction site through the implementation of appropriate erosion and
                                       sediment control measures.
               8.     Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               9.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
                      LANDSCAPING - PRIOR TO COMMENCEMENT OF WORKS
               10.    Prior to any works commencing.
                      a.      Deleted.




                                                                                                          Page 8 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 9

                      LANDSCAPING - DURING CONSTRUCTION
               11.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice.
                      (* Refer to Advisory Note)
               12.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.
               13.    Landscape works must:
                      a.      Ensure amenity or sales signage and ancillary infrastructure is not installed within the
                              road reserve.
                      b.      Ensure permanent irrigation is not installed within the road reserve.
                      c.      Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
                              foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
                              applied to all planting areas to ensure a minimum 100mm depth once settled.
                      DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use approval
                              MCU22/0196 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Works within Road Reserve/Reinstatement
               17.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               18.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               19.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.



                                                                                                        Page 9 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 10

                      Pathways
               20.    All pathways must be constructed in accordance with the following requirements:
                      a.      All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
                      b.      Provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards.
                      c.      All paths must have a slip resistant surface.
                      d.      Expansion and contraction joints must provide a flush finish. Installation of joints by
                              saw cutting is preferred to ensure a smooth ride for cyclists.
                      e.      The required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard.
               21.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety.
                      b.      be designed and constructed to comply with the Disability Discrimination Act (DDA),
                              Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
                              access and mobility.
                      Site Access and Driveways
               22.    Driveway crossovers must be constructed in accordance with council’s Standard Drawings
                      RS-049, RS-050 and any associated addendum.
               23.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               24.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete;
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway;
                      d.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path.; and
                      e.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works..
                      Earthworks and Retaining Walls
               25.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council prior to the
                      commencement of the use.




                                                                                                       Page 10 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 11

               26.    All Dewatering activities and the treatment of Acid Sulfate Soils must be undertaken in
                      accordance with the following technical reports:
                      a.      Pacific Geotech’s Acid Sulfate Soil Report (PG-9236) dated November 2022; and
                      b.      ADG Consulting’s Dewatering Management Plan (ADG1451.22) dated February 2023.
               27.    Fall protection must be provided to retaining walls that are over 1m high.
               28.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;
                      c.      1 in 3 for planted areas; and
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               29.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               30.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g., by blocking or interfering with natural overland flows).
               31.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               32.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               33.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;
                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               34.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               35.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.


                                                                                                      Page 11 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 12

               36.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term. For the
                      purpose of this condition, an effectively stabilised surface is defined as one that does not, or
                      is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
                      lead to sedimentation, or lead to water contamination.
                      Damage to Services and Assets
               37.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION
                      Certification
               38.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
                      As Constructed Plans and ADAC XML Files (Council)
               39.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files);
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection;
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the relevant
                                       descriptions of assets, services and structures; and
                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels and
                                       applicable survey datum; and
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.




                                                                                                           Page 12 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 13

                      On Maintenance
               40.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
                      achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit;
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy; and
                      c.      maintenance and operational manuals for all proprietary or site specific devices.
                      Off Maintenance
               41.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               42.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements; and
                      b.      submitted certification falsely states works comply with approval requirements.
               43.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      General Advisory Notes
               2.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-
                      050 and RS-056.
               3.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               4.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               5.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.


                                                                                                       Page 13 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 14

                      Prestart, On and Off Maintenance Inspections Request
               6.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               7.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               8.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Environmental Advisory Notes
               9.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               10.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               11.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               12.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               13.    The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Qualified Person
               14.    Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.
                      b.      Undertaking landscape construction and establishment works is considered to be a
                              person with five years current experience in commercial landscape construction
                              projects.
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.


                                                                                                       Page 14 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 15

               9.        FURTHER DEVELOPMENT PERMITS REQUIRED

                   Type of Development Permit Required                           Subject of the required Development Permit

                   Development Permit for Building Works                         All building work

               10.       SUBMISSIONS

               Not applicable.
               11.       RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               12.       OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,



               Matt Pinese
               Development Planner



               Enc:      Appeal Rights
                         Approved Plans/Documents

               DECISION NOTICE HISTORY
               •     Original Decision Notice – 21 July 2023.
               •     Negotiated Decision Notice - 10 October 2023, with an amendment to conditions 3 & 5 for Material Change of Use and additional
                     conditions for Operational Works 1 through to 43

               •     Decision Notice - Minor – 17 October 2025, with an amendment to condition 3 and delete condition 10 of Material Change of Use,
                     amendment to condition 1 and delete condition 10a of Operational Works..




                                                                                                                                 Page 15 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Page 16

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 16 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025

Used in these records

About this file

File size
208 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - MCU22 0196 01 & OPW22 0295 01 (As Published).pdf · 208 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.