Minor Change Existing Approval - MCU22 0196 01 & OPW22 0295 01 (As Published) · MCU22/0196.01
CD-102 B Upper Floor Plan, prepared by, Project 22/09/2023
Urban
CD-200 A Construction Details, prepared by, Project 23/06/2023
Urban
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 16 October 2025, unless an application to extend the currency period
is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
3. All necessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
4. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
5. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
6. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works; and
b. Other relevant parties
7. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
a. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction;
b. Maintenance of safe vehicle and pedestrian access across the frontage of the site
both during daily construction and after daily construction has ceased;
c. Proposed fencing to the site during the construction phase of the development;
d. Adequate parking arrangements for construction workers; and
e. Maintenance and protection of water quality and existing drainage lines through
the construction site through the implementation of appropriate erosion and
sediment control measures.
8. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
9. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
LANDSCAPING - PRIOR TO COMMENCEMENT OF WORKS
10. Prior to any works commencing.
a. Deleted.
Page 8 of 16
Document Set ID: 24236900
Version: 4, Version Date: 22/10/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - MCU22 0196 01 & OPW22 0295 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 208 KB (small file)
- File type
No other editions are linked here.