Decision Notice - Approved by Delegation of Authority MCU21 0182
Officer: Maxwell Potter Direct Telephone: 53296245 Our Reference: MCU21/0182 OPW21/0291, RAL21/0024 Your Reference: 0244 14 March 2022 Three F Pty Ltd C/- Pivotal Perspective Pty Ltd 4/59 Mary St NOOSAVILLE QLD 4566 [email protected] Dear Sir/Madam, Decision Notice Planning Act 2016 I refer to your application and advise that on 10 March 2022, Council decided to approve the application, subject to conditions. Details of the decision are as follows: application details Application No: MCU21/0182, RAL21/0024 & OPW21/0291 Street address: 19 Werin St Tewantin Qld 4565 Real property description: Lot 1 RP 88534 Planning Scheme: Noosa Plan 2020 (25 September 2020) Decision details Council decided to issue the following type of approval: Development Permit for Material Change of Use - Dual occupancy, Reconfiguration of a Lot (1 into 2 lots and common property) and Operational Works (Engineering, Carparking and Landscaping) CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions MATERIAL CHANGE OF USE - MCU21/0182 PLANNING When Conditions must be Complied With Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues. Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table. These plans must be amended in accordance with the conditions. Plan No. Rev. Plan/Document Name Date 2B . Site plan/detail survey, prepared by and+design MAR 2021 3B . Floor plans, prepared by and+design MAR 2021 4B . Elevations, prepared by and+design MAR 2021 211207 02 a Specification as prepared by Seed landscape design as amended by Conditions DEC 2021 211207 03 d Landscape Plan as prepared by Seed landscape design as amended by Conditions FEB 2021 211207 04 d Planting Plan as prepared by Seed landscape design as amended by Conditions FEB 2021 211207 05 d Planting Schedule as prepared by Seed landscape design as amended by Conditions FEB 2021 211207 06 a Details as prepared by Seed landscape design as amended by Conditions DEC 2021 211207 07 b Details as prepared by Seed landscape design FEB 2021 Currency Period This development approval lapses if the use has not happened by 10 March 2028, unless an application to extend the currency period is approved by Council. Building Height The maximum height of the development must not exceed 8 metres above the finished ground level and the natural ground level. Certification must be submitted to Council from a Licensed Surveyor which certifies that the building does not exceed the maximum height requirement of this Decision Notice. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. Street Identification The street address of the development must be clearly visible and discernible from the primary frontage of the site by the provision of a street number and, where appropriate, the building name. Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site. Building Appearance All air conditioning units or other mechanical equipment must be fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties. Clothes Drying Areas Each dwelling unit must be provided with access to an outdoor clothes line which is screened from public view. Fencing and Walls Any street fencing must be set back an average of 1 metre from the front property boundary. Any fencing on the front boundary must either: not exceed a maximum height of 1.2m be of open construction. Any street fencing must be articulated by stepping the design at a maximum of every 5m. The area of land between any street fence and the front property boundary must be densely landscaped to screen any fencing from the street. Both side and rear fencing must not exceed a maximum height of 1.8m. Landscaping Works The development site must be landscaped in accordance with PSP3 – Landscaping Plants and Guidelines and generally in accordance with the approved plans. All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. All landscape works must be maintained generally in accordance with the approved design for the life of the development. All mature trees within the road reserve must be retained in accordance with the approved landscape plan unless prior written authorisation from Council is gained for removal. The existing mature Poinciana tree located on the front/southern side boundary and included within Approved Plans must be retained and protected during construction. ENGINEERING Site Access and Driveways A sealed access driveway must be provided from Werin Street to all parking and manoeuvring areas of the development. The works must include in particular: A driveway crossover in accordance with Councils standard drawings RS-049 and RS-050 and approved plan 31110-OW4.1 (Rev A) as prepared by SCG Consulting. On site turning for vehicles exiting the site from the rear new unit. Car Parking A minimum of three (3) car parking spaces must be provided on the site and must include in particular: Two covered spaces; and One additional space. Stormwater Drainage The site must be provided with a stormwater drainage system connecting to a lawful point of discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM) and generally in accordance with approved plan 31110-SW1.1 (Rev A) as prepared by SCG Consulting. Services Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications. Certification must be submitted to Council from all relevant service providers (Energex, NBN and Unitywater) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction. Earthworks and Retaining Walls All fill and associated batters must be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. RECONFIGURING OF A LOT – RAL21/0024 Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table. These plans must be amended in accordance with the conditions. Plan No. Rev. Plan/Document Name Date 3 . Subdivision Plan, prepared by and+design MAR 2021 All lot numbering on the subdivision plan to be submitted to Council for compliance assessment must remain as shown on the Approved Plans. The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions. Currency Period This development approval lapses if the requirements of the conditions have not been completed and an application for plan seal is not lodged with Council by 10 March 2026, unless an application to extend the currency period is approved by Council. Community Management Statement Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the subdivision plan to Council for compliance assessment. Prior to the submission of the subdivision plan to Council for plan sealing, all conditions of this Development Approval, Development Approval MCU21/0182 and any associated operational works approvals must be completed and accepted by Council. OPERATIONAL WORKS – OPW21/0291 Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table. These plans must be amended in accordance with the conditions. Plan No. Rev. Plan/Document Name Date 31110-CS . Operational Works: Cover Sheet as prepared by SCG Consulting Engineers October 2021 31110-OW1.1 . Operational Works: Survey & Existing Services as prepared by SCG Consulting Engineers October 2021 31110-OW2.1 . Operational Works: Silt & Sediment Control as prepared by SCG Consulting Engineers October 2021 31110-OW3.1 B Operational Works: Bulk Earthworks as prepared by SCG Consulting Engineers 18 January 2022 31110-OW4.1 B Operational works: Driveway & Access as prepared by SCG Consulting Engineers 18 January 2022 31110-OW4.2 . Operational Works: Driveway Details as prepared by SCG Consulting Engineers October 2021 31110-OW4.2 A Operational Works: Vehicle Manoeuvring as prepared by SCG Consulting Engineers 18 January 2022 31110-SW1.1 B Operational Works: Stormwater Management as prepared by SCG Consulting Engineers 18 January 2022 211207 02 a Specification as prepared by Seed landscape design as amended by Conditons DEC 2021 211207 03 d Landscape Plan as prepared by Seed landscape design as amended by Conditons FEB 2021 211207 04 d Planting Plan as prepared by Seed landscape design as amended by Conditons FEB 2021 211207 05 d Planting Schedule as prepared by Seed landscape design as amended by Conditons FEB 2021 211207 06 a Details as prepared by Seed landscape design as amended by Conditons DEC 2021 211207 07 b Details as prepared by Seed landscape design FEB 2021 Currency Period The Currency Period for this development approval lapses if the development has not substantially started by 10 March 2024, unless an application to extend the currency period is approved by Council. PRIOR TO COMMENCEMENT OF WORKS Engineering All necessary approvals from external service providers (e.g. Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; Erosion and sediment control works; and Other relevant parties A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction; Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased; and Proposed fencing to the site during the construction phase of the development Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures; Include a post out to the local residents and businesses advising of the proposed development, the expected time frames and the site contact details; Include signage in prominent locations on the boundaries of the site advising of the proposed development, the expected time frames and the site contact details; Any changes to the details associated with the Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. Landscaping Amended plans must be submitted to Council prior to the pre-start meeting and must include the following: Plant species selected for screening in particular along all boundary fences including the street boundary must reach a minimum 4.6 metres at maturity. It is noted for example Westringia ‘wynyabbie Gem’ reaches a height of 2 metres which is not appropriate for use as a screening plant and has been included for use in multiple sections of the boundaries for screening purposes on the Landscaping Plan. Details of the front landscaping garden including what is proposed being a 2 metre wide landscaping garden along the frontage with no front fencing. The development site must be landscaped. The works must be undertaken in accordance with the Operational Works approval OPW21/0291 and the Noosa Plan for that specific area and must include in particular: the works shown on the Amended Plans submitted to Council; landscaping to the north, east and southern boundaries must create a screen with a minimum height of 4 – 6 metres; provision of 2 street trees within the road reserve as detailed within the Approved Plans and ensuring: Noosa Native preferred species; 45 litre pot size; a minimum of 1 metre behind the back of the kerb; and NATSPEC certification. The existing mature Poinciana tree located on the front/southern side boundary and included within Approved Plans must be retained and protected during construction. All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. Prior to requesting a prestart meeting: Tree protection fencing must be installed under the supervision of a qualified person*. (Refer to Advisory Note) A condition report including photographs of the frontage of the site must be completed and submitted to Council at the prestart meeting. DURING CONSTRUCTION Engineering All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice; The relevant conditions of the higher order Material Change of Use/Reconfiguration of Lot approval viz. MCU21/0182 & RAL21/0024 to which this approval relates; All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; and The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. Works within Road Reserve/Reinstatement Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Pathways Trench width cuts across footpaths are not permitted. Whole footpath panels must be replaced in the footpath where services are installed across footpath alignments. All pathway modification must be constructed in accordance with the following requirements: All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065. Provision must be made for disabled access at all kerb crossings associated with pathways, in accordance with Council's current standards. All paths must have a slip resistant surface Expansion and contraction joints must provide a flush finish. Installation of joints by saw cutting is preferred to ensure a smooth ride for cyclists The required work includes any modifications to ensure the footpath finishes flush with all existing service covers and the like, or alternatively these services are raised or altered, so as not to create a pedestrian safety hazard Site Access and Driveways Driveway crossovers must be constructed in accordance with Council’s Standard Drawings RS-049 and RS-050. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete. The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks and Retaining Walls All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with the standard. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods, Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods, Been revised to address predicted rainfall events, and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring. The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: Where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or Where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. Environment Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (*Refer to Advisory Notes). Limit soil exposure on the site to a distance of no more than 2m beyond the extent of earthworks shown on the approved plans except where the exposed soil is effectively stabilised without delay and prior to rainfall occurring. Retention of Existing Trees and Vegetation All trees and vegetation identified for retention must be protected in accordance with AS 4970, Protection of trees on development sites by a qualified person*. (*Refer to Advisory Notes). Removal of Existing Trees and Vegetation All tree and vegetation removal works must be undertaken by a qualified person*. *(Refer to Advisory Note) Vegetation removal or pruning must be undertaken in a manner that avoids damaging surrounding vegetation and habitat. Fauna or fauna habitat relating to minor approved tree removal/clearing works must be managed by a qualified person*. *(Refer to Advisory Note) Landscaping Works Landscape works must be supervised, undertaken and certified by qualified persons*. All works must be completed in accordance with this Decision Notice. (* Refer to Advisory Note) Landscape works must: Delineate all planting to grassed area interfaces with an edge as detailed within the approved plans. Ensure amenity or sales signage and ancillary infrastructure is not installed within the road reserve. Ensure permanent irrigation is not installed within the road reserve. Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of foreign matter including anthropogenic waste, rock, soil/sediment contamination and is applied to all planting areas to ensure a minimum 100mm depth once settled. Ensure finished level of all mulch in garden beds is to be a minimum of 50mm below the level of the adjacent top of kerb. *(Refer to Advisory Notes) Provision of turfed area to road frontages. Turfed areas must be must be free of pest, diseases and weeds and level with adjoining surfaces. Soil for landscaping must provide for healthy and sustained site specific vegetation performance. (for larger sites) All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. Fencing and walls Fencing must: Be type, height and location as detailed within the approved higher order MCU21/0182 and RAL21/0024 and approved landscaping plans. Be located wholly within lot boundaries. Have a design life commensurate with the new buildings. Not include CCA (copper chrome arsenic) timber products. Be finished in neutral colour tones that blend with the surrounding landscape. FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection. Supervision/Certification Prior to commencement of use the following (prepared by respective qualified persons* and certifying compliance with approvals) must be submitted to Council: Landscaping certification confirming all works have been constructed in accordance with conditions of approval. NATSPEC certification (Specifying Trees: a guide to assessment of tree quality addressing each specimen). (* Refer to Advisory Note) Bonds Bonds must: Meet the requirements of the relevant Council Planning Scheme Policy for performance and uncompleted works. Be calculated using a schedule of works and relevant bond equation. Include GST. Have approval of the bond calculations and amount from Council, prior to lodgement. Be lodged with Council and accompanied by the Bond Administration Fee/s. Be requested for release by writing to Council, when relevant approval requirements have been met. On Maintenance Maintenance periods* must be: 12 months for Streetscape and Amenity Landscape. *(Refer to Advisory Note) Prior to commencement of use / requesting an On Maintenance inspection the following (prepared by respective qualified persons* and certifying compliance with approvals) must be submitted to Council: Landscaping certification. Specifying Trees: a guide to assessment of tree quality (NATSPEC) certification (addressing each specimen). Off Maintenance Prior to requesting an Off Maintenance inspection the developer must: Provide a written request for the Off Maintenance inspection; and Written request of bond release. *(Refer to Advisory Note) referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: Infrastructure Charges All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges Building and Construction Industry (Portable Long Service Leave) Levy The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. General Advisory Notes As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-049 and RS-050. Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise Tree Protection Bond may be drawn upon by Council if any trees identified for retention are damaged to the point where they cannot be saved (as confirmed by the site Arborist and agreed in writing by Council). Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection: Methods of stabilisation are: appropriate for slopes and slope lengths; and are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. If at the time of request for plan sealing, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability: evidence that the site has been effectively stabilised in the short term; evidence that soil has been adequately ameliorated; evidence that seed of annual and perennial grass species has been applied at an adequate rate; and that grass seed has germinated at a density that is likely to achieve an effective grass cover. Resubmission of Amended Documents Required The conditions of this Decision Notice require resubmission of the referenced Landscape Plans to Council with amendments. Please address the amended document to Council’s Planning Assessment Branch with the Reference No. MCU21/0182, prior to the Operational Works pre-start as detailed within conditions included within the Decision Notice. Should the amended document not be submitted, the applicant is advised that the required Operational Works pre-start meeting will not be approved. Retention of Existing Trees The existing trees on adjoining properties must be retained and protected during construction wherever achievable. To avoid doubt, this advisory note is not intended to exclude the operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following construction of the development which is the subject of this development approval. Qualified Person Qualified Person, for the purpose of: Supervising landscape works and preparing a landscape certification, is considered to be a landscape architect, landscape designer or horticulturist with a minimum of three years current experience in the field of landscape design. Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either: International Society of Arboriculture (ISA) certification; or A Diploma of Arboriculture. Managing Fauna protection is considered to be a certified Fauna Spotter Catcher. Landscape Works The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges Register where: An inspection revealed that any constructed rehabilitation/landscape works do not comply with the conditions of the Decision Notice, Approved Plans and or Approved Documents Certification is submitted to Council falsely stating that works comply with the approved plans, documents and or conditions of the Decision Notice. Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. On Maintenance Request for On Maintenance is the responsibility of the developer. No credit will be given due to failure to request inspection. Maintenance works are the responsibility of the developer and must include regular inspections, repairs, rectifications and establishment. A single maintenance run immediately prior to inspection is not acceptable. Off Maintenance A re-inspection fee in accordance with Councils Fees and Charge Register will be charged where: A Council inspection reveals works do not comply with approval requirements. Submitted certification falsely states works comply with approval requirements. property notes Not applicable. VARIATION approval details A variation approval varying the effect of the planning scheme has been granted and as such the category of assessment and assessment benchmarks applying to the development resulting from this approval are identified in the conditions. further development permits required Type of Development Permit Required Subject of the required Development Permit Development Permit for Building Works All building work. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. Yours faithfully, Maxwell Potter Graduate Development Planner Enc: Appeal Rights Infrastructure Charge Notice Approved Plans/Documents Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017 Chapter 6 Dispute resolution Part 1 Appeal rights 229 Appeals to tribunal or P&E Court (1) Schedule 1 of the Planning Act 2016 states – (a) Matters that may be appealed to – (i) either a tribunal or the P&E Court; or (ii) only a tribunal; or (iii) only the P&E Court; and (b) The person- (i) who may appeal a matter (the appellant); and (ii) who is a respondent in an appeal of the matter; and (iii) who is a co-respondent in an appeal of the matter; and (iv) who may elect to be a co-respondent in an appeal of the matter. (2) An appellant may start an appeal within the appeal period. (3) The appeal period is – (a) for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or (b) for an appeal against a deemed refusal – at any time after the deemed refusal happens; or (c) for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or (d) for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or (e) for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or (f) for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person. Note – See the P&E Court Act for the court’s power to extend the appeal period. (4) Each respondent and co-respondent for an appeal may be heard in the appeal. (5) If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal. (6) To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about- (a) the adopted charge itself; or (b) for a decision about an offset or refund- (i) the establishment cost of trunk infrastructure identified in a LGIP; or (ii) the cost of infrastructure decided using the method included in the local government’s charges resolution. 230 Notice of appeal (1) An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that- (a) is in the approved form; and (b) succinctly states the grounds of the appeal. (2) The notice of appeal must be accompanied by the required fee. (3) The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to – (a) the respondent for the appeal; and (b) each co-respondent for the appeal; and (c) for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and (d) for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and (e) each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and (f) for an appeal to the P&E Court – the chief executive; and (g) for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate. (4) The service period is – (a) if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or (b) otherwise – 10 business days after the appeal is started. (5) A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6). (6) A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person. 231 Other appeals (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable. (2) The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error. (3) A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter. (4) In this section – decision includes- (a) conduct engaged in for the purpose of making a decision; and (b) other conduct that relates to the making of a decision; and (c) the making of a decision or failure to make a decision; and (d) a purported decision; and (e) a deemed refusal. non-appealable, for a decision or matter, means the decision or matter- (a) is final and conclusive; and (b) may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and (c) is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground. 232 Rules of the P&E Court (1) A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal. (2) However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court [word/footer1.xml] Page 16 of 16 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 16 [Attachment: image3.png (image text)] ee) NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.