                                                                                   PO Box 141, Tewantin, QLD 4565
                                                                                   Phone (07) 5329 6500         Fax (07) 5329 6501
                                                                                   Email: [email protected] Website: www.noosa.qld.gov.au
                                                                                   ABN 97 969 214 121



                             INFRASTRUCTURE CHARGES NOTICE

          To:      Synergy Property Partners                                                     Infrastructure Charges Notice No: N1120
                   C/- TFA Project Group                                                                                Revision No:   0
                   PO Box 301
                   ALBION QLD 4010                                                                                     Date of Issue: 29 April 2016


          Notice is hereby given under the Sustainable Planning Act 2009 and the Local Government Act 2009
          that the infrastructure charge notice is levied by the Noosa Shire Council on the described land.

          DEVELOPMENT TO WHICH THE INFRASTRUCTURE CHARGE APPLIES:
            Development Approval Reference:                    REC15/0022
            Type of Development Approval:                      Reconfiguration of a Lot

          LAND TO WHICH THE INFRASTRUCTURE CHARGE APPLIES:
            Land Description:                                  Lot 30 SP 170751
            Address:                                           115 Eumundi Noosa Road NOOSAVILLE

          INFRASTRUCTURE CHARGE LEVIED BY COUNCIL:
          In accordance with Noosa Shire Council Charges Resolution (No.2) 2014 (effective 16 February 2015)
                                        CALCULATED INFRASTRUCTURE CHARGE (Current at Base Date 1 July 2014) =                                      $33,600.00

                                                                       Parks Contribution paid under previous Lot Reconfiguration
                                          Other                                                                                                     $2,520.00
                                                                       approval 23134 DA (re Stage 3 creation of Lot 30)

                    REDUCTIONS            Additional                   Not Applicable                                                                   $0.00

                                          Trunk infrastructure Offset Not Applicable                                                                    $0.00

                                 *NET INFRASTRUCTURE CHARGE PAYABLE (Current at Base Date 1 July 2014) =                                         $31,080.00


          * SUBJECT TO AUTOMATIC INCREASE PROVISION:
          The net infrastructure charge amount payable is subject to automatic indexation from the base date to the time of
          making payment. Indexation is applied using variations in the Consumer Price Index at the times applicable limited
          to the “maximum amount” possible to be issued under the State Planning Regulatory Provision (adopted charges)
          as amended by the Minister and in accordance with the legislation at the time of issue and payment.

                CONTACT COUNCIL PRIOR TO MAKING PAYMENT FOR THE CURRENT AMOUNT DUE.

          The Calculated Infrastructure Charge details are provided on page 3 of this notice.
                (NOTE: Separate Infrastructure Charges may be issued by Unitywater as applicable)

          DATE FOR PAYMENT OF THE INFRASTRUCTURE CHARGE
          Under the Sustainable Planning Act 2009, the Infrastructure Charge is to be paid to NOOSA COUNCIL
          as follows:

              DEVELOPMENT PERMIT TYPE                                                    DUE DATE FOR PAYMENT
                                                             When Council approves the plan of subdivision for the
            Reconfiguration a Lot
                                                             reconfiguration




                                               PO Box 141                        P. (07) 5329 6500            [email protected]
                                               TEWANTIN QLD 4565                 F. (07) 5329 6501            www.noosa.qld.gov.au             ICN - Page 1
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                                                Print Date: 29 April 2016, 4:54 PM
Log in to download the original file

ICN.PDF · 353 KB (small file)

Full text of the other 5 pages

Page 2

Noosa Council documents


          REFUND PROVISION:
          Where the value of a “Trunk” Infrastructure Offset exceeds the Net Infrastructure Charge Payable, a
          refund will be provided in accordance with Clause 12.4 of Council’s Resolution.

                                       TERMS OF REFUND                                             REFUND AMOUNT
            Not Applicable                                                                                                $0.00

          INFRASTRUCTURE CHARGES TAKEN TO BE A RATE:
          Under the Sustainable Planning Act 2009 an infrastructure charge levied by a local government is, for
          the purposes of recovery, taken to be a rate within the meaning of the Local Government Act 1993.
          This means:
             a.   an adopted infrastructure charge may be recovered by court action for a debt;
             b.   an adopted infrastructure charge may be recovered from the person for the time being
                  owning the relevant land, regardless of who was the owner or other person upon whom the
                  charges was imposed;
             c.   Interest is payable on overdue payments; and
             d.   If charges are unpaid for 3 years, the land can be sold to recover the outstanding charges.

          INTEREST ON OVERDUE CHARGES:
          Compound interest at the rate of 11% per annum calculated daily is payable on all infrastructure
          charges outstanding after the due date shown on this charges notice.

          GOODS AND SERVICES TAX:
          The federal government has determined that rates and utility charges levied by local government will
          be GST free. Accordingly, no GST is included in this infrastructure charges notice.

          INFRASTRUCTURE CHARGES ENQUIRIES:
          Enquiries regarding this infrastructure charges notice should be directed to Council’s office:
              Phone (07) 5329 6211 or 5329 6449 during office hours; or
              E-mail: [email protected]

          METHODS OF PAYMENT:
                                       Cheque or money order to be made payable to: Noosa Council
            Mail
                                       PO Box 141, Tewantin, QLD 4565

                                       Noosa Council Tewantin office: 8.30 am to 4.30 pm Monday to Friday
            In Person
                                       (excludes public holidays)
                                       Mastercard or Visa only
            Credit Card                Note: All payments made by credit card will incur a 0.55% surcharge to reflect
                                       the cost of fees charged for credit card transactions.
                                       Payment by electronic transfer direct to Council’s Bank Account is only
            Direct Bank Transfer
                                       available by special arrangement. Contact Infrastructure Enquiries.


          NOTES:
          Nil




                                        PO Box 141                P. (07) 5329 6500   [email protected]
                                        TEWANTIN QLD 4565         F. (07) 5329 6501   www.noosa.qld.gov.au         ICN - Page 2
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                    Print Date: 29 April 2016, 4:54 PM

Page 3

Noosa Council documents


        INFRASTRUCTURE CHARGE CALCULATION DETAILS:
        The infrastructure charge is calculated in accordance with Council’s Infrastructure Charges Resolution incorporating the charge apportionment (break-
        up) agreement with Unitywater in compliance with the Sustainable Planning Act 2009 and Statutory Regulatory Provision (adopted charges) applying
        at the time of issuing the notice.
         NOOSA SHIRE COUNCIL CHARGES RESOLUTION (No.2) 2014 (Effective 16 February 2015)
         INFRASTRUCTURE CHARGE CALCULATION                                                                                                                                                                                       Base Date:             01-July-2014
                                                                                                                                                           Colum n 7
                              Colum n 1
                       Use under The Noosa Plan
                                                                                                                                                            COUNCIL                                      Council Charge Calculation
                                                                                                                                                            CHARGE
                                                                      Colum n 2                            Colum n 3
                                                                                                                                                          Per Table 10.1                                     EXISTING                NET
                                                                  Developm ent class                    Unit of m easure
                                                                                                                                                  (Charges breakup) of Adopted        APPROVED                                                       CHARGE AMOUNT
                               Defined use                                                                                                                                                                     (QTY)          CHARGEABLE
                                                                                                                                                       Charge in Column 6                 (QTY)                                                               $
                                                                                                                                                     ($ per unit of measure)                                  (Credit)              (QTY)
                                                                                                                  Lot
         Non-Residential (Lot Reconfiguration)                      Non-Residential                                                                           $16,800                        2                                         2                               $33,600
                                                                                           (equivalent to 3 o r mo re bedro o m dwelling unit)

                                                                                                                                                                                                     Sub-Total, Non-Residential =                                  $33,600.00

                            STORMWATER                          ALL Non-Residential Uses                m2 impervious area                                     $10                                                                     0                                $0.00
                 (Non-Residential Development only)



                                                                                                                                             CALCULATED INFRASTRUCTURE CHARGE (Current at Base Date 1 July 2014) =                                                 $33,600.00

                                                                                                                                                                                    Parks Contribution paid under previous Lot Reconfiguration
                                                                                                                                                 Other                                                                                                              $2,520.00
                                                                                                                                                                                    approval 23134 DA (re Stage 3 creation of Lot 30)

                                                                                                         REDUCTIONS                              Additional                         Not Applicable                                                                      $0.00

                                                                                                                                                 Trunk infrastructure Offset Not Applicable                                                                             $0.00

                                                                                                                             *NET INFRASTRUCTURE CHARGE PAYABLE (Current at Base Date 1 July 2014) =                                                              $31,080.00


         ALLOCATION OF LEVIED CHARGE TO TRUNK INFRASTRUCTUE NETWORKS
         The infrastructure charge payable will be allocated to Council “Trunk ” infrastructure network s in accordance with Council’s Resolution as follows:

                                                                                      Column 4
                                                                                                                                                                                                                                                     * Net Infrastructure
                                                                Allocation of Council infrastructure charge to trunk                                                                                        Reductions
            Council “Trunk” Infrastructure Network                                                                                                       Calculated                                                                                    Charge Payable
                                                                              infrastructure networks
                         (Table 10.2)                                                                                                              Infrastructure Charge                                                                               (At Base Date:
                                                               Residential Development        Non-Residential Development                                                                 Other                Rebate               Offset               1 July 2014)

         Transport            (Charge Type: icA3trans)                   40%                                     85%                                                 $28,560.00                   $0.00               $0.00                  $0.00                 $28,560.00
         Public Parks & Land for Community Facilities
                                                                         50%                                     15%                                                    $5,040.00           $2,520.00                 $0.00                  $0.00                  $2,520.00
                              (Charge Type: icA3parkCF )

         Stormwater          (Charge Type: icA3storm )                   10%                                    100%                                                       $0.00                  $0.00               $0.00                  $0.00                      $0.00

                 * Subject to Automatic Increase Provision until date of payment.                          *TOTALS =                                                 $33,600.00             $2,520.00                 $0.00                  $0.00                 $31,080.00


        #
         For non-residential development, Stormwater infrastructure charges are not applied on Reconfiguration of a Lot approvals but will apply and be issued on subsequent development
                                                  2
        approvals that identifies the applicable m impervious area of the development on the site.



                                                                                                   PO Box 141                                            P. (07) 5329 6500              [email protected]
                                                                                                   TEWANTIN QLD 4565                                     F. (07) 5329 6501              www.noosa.qld.gov.au                     ICN - Page 3
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                                                                                                                                                                    Print Date: 29 April 2016, 4:54 PM

Page 4

Noosa Council documents


                                                                  PO Box 141, Tewantin, QLD 4565
                                                                  Phone (07) 5329 6500         Fax (07) 5329 6501
                                                                  Email: [email protected] Website: www.noosa.qld.gov.au
                                                                  ABN 97 969 214 121


           INFRASTRUCTURE CHARGES INFORMATION NOTICE
          1.      PRELIMINARY

          Infrastructure charges are triggered and issued on development approvals as a contribution towards the
          cost of "trunk" infrastructure provided to service development.
          For development approved prior to 1 July 2011, infrastructure contributions and (ICP) charges continue to
          apply in accordance with the development approval conditions and or infrastructure charge notices (ICP)
          issued under legislation current at the time those approvals & charge notices were issued.
          For development approved from 1 July 2011, adopted infrastructure charges are governed by local
          government adopted infrastructure charges resolutions in accordance with the "Sustainable Planning Act
          2009 (SPA)" and “State Planning Regulatory Provision (adopted charges) (SPRP)”.
          The Sustainable Planning (Infrastructure Charges) and Other Legislation Amendment Bill 2014 introduced
          further amendments to SPA that commenced to apply for developments approved from 4 July 2014.
          From 1 July 2014, Infrastructure Charges Notices are issued separately by both Council and Unitywater
          relating to their specified “Trunk” infrastructure networks. All payments (including contributions & charges
          previously issued) are also payable separately to Council and Unitywater respectfully.

          2.      THE DECISION AND REASONS FOR IT

          The Sustainable Planning Act 2009 (as amended), provides for the following:
          (1) Authorises local governments to do the following for development approvals:
                (a) for trunk infrastructure, either or both of the following—
                    (i) adopt, by resolution, charges for development infrastructure and levy charges in accordance
                         with the resolution;
                    (ii) impose particular conditions about development infrastructure;
                (b) for non-trunk infrastructure, impose particular conditions about development infrastructure; and
          (2) Provides for a State planning regulatory provision to govern local government adopted charges and
              charges by distributor-retailers under the SEQ Water Act for trunk infrastructure.
          Noosa Council decided to apply infrastructure charges on development under its adoption of the "Noosa
          Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to replace the "Sunshine Coast
          Regional Council Adopted Infrastructure Charges Resolution (No.4) 2011" that translated across to Noosa
          Council on 1 January 2014. The resolutions also detail the apportionment (break-up) agreement with
          Unitywater.
          On 12 February 2015, Noosa Council Adopted the "Noosa Shire Council Charges Resolution (No.2) 2014" to
          replace the "Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to comply with
          the requirements of the SPA amendments dated 4 July 2014 and amended (break-up) agreement with
          Unitywater. The resolution takes effect and applies to new approvals issued from Monday 16 February 2015.

          3.      INFRASTRUCTURE CHARGE NOTICES

          3.1     TRIGGERS FOR INFRASTRUCTUE CHARGES & ISSUING OF NOTICES
          The triggers for issuing infrastructure charges are defined in the SPA and SPRP and are generally triggered
          by the issue of a development permit for either:
          (1) Reconfiguration of a lot; or
          (2) Material Change of Use of Premises; or
          (3) Building Works issued by a Private Certifier.




                                         PO Box 141              P. (07) 5329 6500    [email protected]
                                         TEWANTIN QLD 4565       F. (07) 5329 6501    www.noosa.qld.gov.au          ICN - Page 4
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                     Print Date: 29 April 2016, 4:54 PM

Page 5

Noosa Council documents


          Under the SPA, infrastructure charges are not imposed by condition on a development permit - they are an
          action that follows the issue of a permit. So consequently, charges may be imposed in cases where a
          development permit for a lot reconfiguration or material change of use of premises has previously been
          granted, but a development permit for building works is yet to issue.
          3.2     DUE DATE FOR PAYMENT OF INFRASTRUCTUE CHARGES (SPA SECTION 638)
          (1) A levied charge becomes payable—
                (a) if the charge applies for reconfiguring a lot—when the local government that levied the charge
                    approves the plan of subdivision for the reconfiguration; or
                (b) if the charge applies for building work—when the certificate of classification or final inspection
                    certificate for the building work is given; or
                (c) if the charge applies for a material change of use—when the change happens; or
                (d) if the charge applies for other development—on the day stated in the infrastructure charges notice
                    under which the charge was levied.
          (2) This section is subject to section 639.
          3.3     EFFECT OF CHARGES NOTICE (INFRASTRUCTURE CHARGES TAKEN TO BE A RATE)
          An infrastructure charge levied by a local government is, for the purposes of recovery, taken to be a rate
          within the meaning of the Local Government Act 1993. This means:
          (1) an infrastructure charge may be recovered by court action for a debt;
          (2) an infrastructure charge may be recovered from the person for the time being owning the relevant
              land, regardless of who was the owner or other person upon whom the charges was imposed;
          (3) INTEREST IS PAYABLE on overdue payments; and
          (4) if charges are unpaid for 3 years, THE LAND CAN BE SOLD to recover the outstanding charges.
          3.4     INTEREST ON OVERDUE INFRASTRUCTURE CHARGES
          Compound interest at the rate of 11% per annum calculated daily is payable on all overdue infrastructure
          charges outstanding after the due date for payment as applying to the infrastructure charges notice.
          3.5     GOODS AND SERVICES TAX
          The federal government has determined that rates and utility charges levied by local government will be
          GST free. Accordingly, no GST is included in this infrastructure charges notice.

          4.      APPEALS ABOUT INFRASTRUCTURE CHARGES NOTICE

          Prior to making an appeal about an infrastructure charge notice, the recipient must first make
          representations to the infrastructure charges notice in accordance with SPA sections 640 to 644.
          4.1     APPEALS ABOUT INFRASTRUCTURE CHARGES NOTICE (SPA SECTION 478)
           (1) The recipient of an infrastructure charges notice may appeal to the court about the decision to give the
               notice.
          (2) However, the appeal may be made only on 1 or more of the following grounds—
              (a) the charge in the notice is so unreasonable that no reasonable relevant local government could have
                  imposed it;
              (b) the decision involved an error relating to—
                  (i) the application of the relevant adopted charge; or
                  (ii) the working out, for section 636, of additional demand; or
                  (iii) an offset or refund;
              (c) there was no decision about an offset or refund;
                (d) if the infrastructure charges notice states a refund will be given—the timing for giving the refund.
          (3) To remove any doubt, it is declared that the appeal must not be about—
                (a) the adopted charge itself; or
                (b) for a decision about an offset or refund—


                                         PO Box 141               P. (07) 5329 6500   [email protected]
                                         TEWANTIN QLD 4565        F. (07) 5329 6501   www.noosa.qld.gov.au         ICN - Page 5
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                    Print Date: 29 April 2016, 4:54 PM

Page 6

Noosa Council documents


                   (i) the establishment cost of infrastructure identified in an LGIP; or
                   (ii) the cost of infrastructure decided using the method included in the local government’s charges
                        resolution.
          (4) The appeal must be started within 20 business days after the day the recipient is given the relevant
              infrastructure charges notice.
          4.1       HOW APPEALS TO THE COURT ARE STARTED (SPA SECTION 481)
          (1) An appeal is started by lodging written notice of appeal with the registrar of the court.
          (2) The notice of appeal must state the grounds of the appeal.
          (3) The person starting the appeal must also comply with the rules of the court applying to the appeal.
          (4) However, the court may hear and decide an appeal even if the person has not complied with subsection
              (3).
          4.2     APPEALS ABOUT INFRASTRUCTURE CHARGES DECISIONS (SPA SECTION 535)
          (1) The recipient of an infrastructure charges notice may appeal to a building and development committee
              about the decision to give the notice.
          (2) However, the appeal may be made only on 1 or more of the following grounds—
                (a) the decision involved an error relating to—
                    (i) the application of the relevant adopted charge; or
                    (ii) the working out, for section 636, of additional demand; or
                    (iii) an offset or refund;
                (b) there was no decision about an offset or refund;
                (c) if the infrastructure charges notice states a refund will be given—the timing for giving the refund.
          (3) To remove any doubt, it is declared that the appeal must not be about—
                (a) the adopted charge itself; or
                (b) for a decision about an offset or refund—
                    (i) the establishment cost of infrastructure in an LGIP; or
                    (ii) the cost of infrastructure decided using the method included in the local government’s charges
                         resolution.
          (4) The appeal must be started within 20 business days after the day the recipient is given the
              relevant infrastructure charges notice.
          4.3     HOW APPEALS TO COMMITTEES ARE STARTED (SPA SECTION 537)
          (1) A person starts an appeal by lodging written notice of appeal, in the approved form, with the registrar
              of building development committees.
          (2) The notice of appeal must state the grounds of the appeal and be accompanied by the fee prescribed
              under a regulation.

          5.      INFRASTRUCTURE CHARGES ENQUIRIES

          Infrastructure charges enquiries should be directed to the appropriate entity as follows:
          (1) Council Infrastructure Charges enquiries should be directed to Noosa Council’s office:
                Phone: (07) 5329 6211 or 5329 6449 during office hours; or
                E-mail: [email protected]
          (2) Unitywater Infrastructure Charges enquiries should be directed to Unitywater’s office:
                Phone: 1300 086 489 or (07) 5431 8333 during office hours; or
                E-mail: [email protected]




                                         PO Box 141               P. (07) 5329 6500   [email protected]
                                         TEWANTIN QLD 4565        F. (07) 5329 6501   www.noosa.qld.gov.au         ICN - Page 6
Document Set ID: 20060089
Version: 1, Version Date: 29/04/2016                                                                    Print Date: 29 April 2016, 4:54 PM

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.