SPECIAL MEETING AGENDA 25 FEBRUARY 2021
Page 95 of 112
21
SCHEDULE 2
Development Obligations schedule
Column 1 | Column 2 Column 3 Column 4 Column 5 Column 6
Item Infrastructure Contribution Specification of the Infrastructure Contribution Value Timing of the | Party responsible for
Infrastructure | the Infrastructure
Contribution Contribution
1.1 Work Contribution to The Work Contribution is generally in accordance | Estimated value As part of Developer
design and construct New with Drawing Numbers 4 to 7 and 9 to 12 in of $1,500,000. Stage 1.
Club House. Schedule 3.
1.2 Work Contribution to fit out | The Work Contribution is such works as required Estimated value As part of Developer
, New Club House. to finish the building to a turn key standard. of $1,000,000. Stage 1.
13 Work Contribution to The Work Contribution provides a minimum of Estimated value As part of Developer
design and construct Car 100 car parking spaces and is generally in of $300,000. Stage 1.
Park. accordance with Drawing Number 4 in Schedule
3.
14 Work Contribution to The Work Contribution is generally in accordance | Not applicable. As part of Developer
, design and construct new with Drawing Number 3 in Schedule 3. Stage 1.
vehicle access road to New
Club House (a shared
access with the seniors
living community).
Document Set ID: 21379346
Version: 1, Version Date: 27/01/2021
22
Column 1 | Column 2 Column 3 Column 4 Column 5 Column 6
Item Infrastructure Contribution Specification of the Infrastructure Contribution Value Timing of the | Party responsible for
Infrastructure | the Infrastructure
Contribution Contribution
15 Work Contribution to The Work Contribution provides storage for a Estimated value As part of Developer
, design and construct golf minimum of 40 buggies plus electric charging of $200,000. Stage 1.
buggy storage shed. ports and is generally in accordance with Drawing
Number 8 in Schedule 3.
1.6 Financial Contribution 1 The Financial Contribution is to be paid when Up to a maximum | As part of Developer
golf membership in the settlement of a dwelling in the seniors living value of Stage 1.
Cooroy Golf Club Inc. for community occurs at the rate of membership for $2,500,000.
each dwelling in the seniors | that year.
living community for a
period of 10 years.
7 Work Contribution to The Work Contribution is generally in accordance | Estimated value As part of Developer
, design and construct with Drawing Numbers 1, 2 and 13 to 18 in of $2,750,000. Stage 1.
retrofits to existing golf Schedule 3.
course layout.
18 Financial Contribution to The Financial Contribution can be used at the golf | $500,000. As part of Developer
, Cooroy Golf Club Inc. for club’s discretion but can include: Stage 1.
course improvements (not
already covered by Golf (a) construction of cart paths in key locations
Course Draft Master Plan across the golf course;
7).
(b) construction of a toilet and shower block
near the current 18th tee suitable for use by
Document Set ID: 21379346
Version: 1, Version Date: 27/01/2021
Page 95 of 112See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.