Skip to the record
The definitive source for everything Noosa Council.

Original source · versioned page text

6.5.22 - Flooding Report 5 may

of 77

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (21.8 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 16, section 1. The text section number identifies this passage in the reader.

      A blockage factor of 20% has been applied as per the ARR blockage assessment completed
      in Appendix E.
      Table 4-2: Model Culvert Information
            ID                       Size                        Length   USIL (m AHD)   DSIL (m AHD)
            1            1 x 1800 x 900mm RCBC                     7.00       14.66          14.56
            2                  1 x 900mm RCP                      11.15       14.08          14.01
            3                  1 x 300mm RCP                      11.17       14.04          13.95
            4                  1 x 300mm RCP                      10.74       13.63          13.60
            5                  1 x 450mm RCP                      10.78       13.13          13.06
            6                  1 x 375mm RCP                      15.00       12.89          12.78
            7                  4 x 750mm RCP                      15.00       12.53          12.49
            8             1 x 300 x 450mm RCBC                    11.83       12.77          12.74
            9                  1 x 380mm RCP                      13.32       13.40          13.30
            10                 1 x 380mm RCP                      11.55       14.60          14.50
            11                10 x 750mm RCP                       11.2       13.95          13.80
            12           3 x 1200 x 900mm RCBC                     11.2       11.94          11.83
            13                1 x 1500mm RCP                       9.79       11.30          11.10
            14                 5 x 900mm RCP                       11.2       15.68          15.62
            15                 1 x 380mm RCP                      10.99       15.95           15.8
            16                10 x 750mm RCP                       11.2       14.05          13.95
            17                 5 x 2400 x 1500                     9.24        6.50           6.40
            18                 1 x 450mm RCP                        6.2        8.72           8.68
         Internal      9 x 1200mm x 600mm RCBC                    10.00       11.80          11.75
        Driveway               1 x 300mm RCP                         5        12.94          12.92



               Model Scenarios
      The Existing (E01) and Proposed (P01) scenarios are described below and depicted in
      Appendix D.

      4.2.1. Existing Scenario (E02)

      In representing the Existing Scenario, the model was setup to represent the overland flow
      characteristics that existed prior to the site being developed. A combination of LiDAR and
      detailed survey was used to represent the existing model terrain. The model was run for the
      63.2%, 39%, 10% and 1% AEP for durations ranging from 30min to 12hrs.

      3.2.3 Proposed Scenario (P03)

      The Proposed Scenario has utilised the Existing Scenario model to represent the proposed
      development. The following changes were made:
           •        Represent internal road at RL12.7m AHD (2d_zsh).
           •        Represent new 9 x 1200 x 600mm RCBC under internal road (1d_nwk).
           •        Represent filling of building envelopes of Lot 1 and 4 to achieve flood immunity
                    (2d_zsh).
           •        Represent minor regrading beside building envelope of Lot 1 (2d_zsh).
           •        Adjustments to roughness to account for new road (2d_mat).
      The model was run for the 63.2%, 39%, 10% and 1% AEP for durations ranging from 60min to
      24hrs.




21-0288-FS001-V5 | Flood Investigation | 60 Glenridge Drive, Cooroibah                                  | 11
Log in to download the original file

6.5.22 - Flooding Report 5 may.pdf · 21.8 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.