NOOSA COUNCIL IDAS Development Application Decision Notice                                                     5 of 10


Roof Water & Stormwater Drainage

25.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
      storage 5000 litres per dwelling) that is installed to ensure water from the tank is used for external uses
      (such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming pools,
      outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All rainwater tanks are to be
      designed and installed in accordance with the Queensland Development Code (QDC), Part 25 –
      Rainwater Tanks, and shall be part of the plumbing application in conjunction with the building approval.
      The location and capacity of the tanks shall be clearly shown on the plans submitted for Building Works /
      Operational Works approval and any overflow shall be directed to the stormwater drainage system located
      at the rear of the site.

      All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
      collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
      drainage permitted to drain from the site shall be discharged to Council’s existing drainage structure at the
      rear of the site.

Sewer Mains

26.   The site shall be connected to Council’s existing sewerage reticulation system that traverses the site at
      the rear of the site and be constructed in accordance with Council’s standards and requirements at no
      cost to Council.
      To ensure Council’s sewer main is accessible for maintenance purposes and is protected from risk of
      damage no structures requiring a building permit (eg. buildings, swimming pools, retaining walls
      exceeding 1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’ (taken as
      the area within a 45-degree angle measured from the invert of the sewer main to the finished surface
      level) or within 1.5m of the centreline of the sewer main, whichever is the greater.

27.   Any landscaping or trees planting on or near the existing sewer and drainage easements at the rear of the
      site shall take into consideration the recommendations of PSP 03 – Item 22 in relation to Planting in
      Vicinity of Sewers and Manholes.

Town Water Supply

28.   The site shall be connected to Council’s existing town water supply and be constructed in accordance with
      Council’s standards and requirements at no cost to Council.

29.   Each individual water connection to the water reticulation system shall extend to the property boundary
      and be metered. All fees for the supply of water meters shall be paid to the Council.

30.   All water meters must be located outside the property boundary and in an easily assessable location to
      facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
      fences or locked gates. In this regard approval of the water meter configuration and location must be
      obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
      hydraulic drawings.

Earthworks

31.   Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
      structures that border the development site. Fences that are affected shall be replaced prior to the
      Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
      clearly shown on the plans submitted for Operational Works approval.

Erosion and Sediment Control

32.   Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
      control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
      waste, will be necessary.

      In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
      to the Council for approval prior to obtaining a Development Permit for Operational Works.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@d8085b9e\@[email protected]

Used in these records

About this file

File size
47 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015A873.001.pdf · 47 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.