Decision Notice OPW14-0119 22 Seahorse Pl Noosaville · OPW14/0119

of 6

Text shows just the words. Original shows the document exactly as it was published.

                                                                              OPW14/0119

4.    No posts or vertical supports of the proposed jetty are to extend vertically from the
      structure unless they provide support for the handrail.

5.    There must be no electrical reticulation system carrying electricity in excess of 24
      volts beyond the revetment wall unless all switches and power outlets are
      positioned above the 1%AEP flood level.

6.    Lighting associated with the use must be designed, installed, operated, and
      maintained in accordance with Section 3 of AS4282 Control of the Obtrusive
      Effects of Outdoor Lighting.

7.    Rock scour protection, wrapped in geotextile, extends 750 mm from the face of the
      revetment wall in this locality. Piles are to be located clear of this rock protection.

8.    The jetty and boat lift are to be used for private purposes only with no commercial
      operations to be undertaken.

9.    Boat repair activities are not permitted on site.

10.   Wastewater and sullage must only be disposed of at approved pumpout facilities.
11.   The mooring facility must not be utilised for live-aboard purposes.

12.   Any construction and post construction activity is not to impact on the condition of
      the waterway, and is to be conducted so as not to breach the Environmental
      Protection Act EPA (1994) and the Environmental Protection (Water) Policy 2009.

13.   The approval or conditions do not constitute a ruling on structural safety and the
      applicant must make their own arrangement to ensure adequacy of design and
      work. Also any approval granted does not warrant that such plans and
      specifications have been checked in detail, nor does it absolve the owner of the
      land from complying with all the conditions of this approval and/or relevant Council
      By-Laws and Policies and/or relevant statues and/or statutory regulations in the
      execution and/or performance of said works. Council does not accept any
      responsibility for the accuracy of such plans and specifications as approved.

14.   Certification by a Registered Professional Engineer of Queensland that states that
      the jetty and boatlift are constructed in accordance with best practice methods and
      are structurally sound must be submitted to Council. A final inspection and
      approval of the structures by Council’s Inspector is also required. Please contact
      Council’s Planning Assessment Section (Development Audit & Response Officer
      0428738563) to arrange the inspection.

15.   This approval lapses where the construction of the jetty and boatlift has not
      commenced within two (2) years of the date of issue of the approval, unless
      application is made and approved by Council for an extension.

16.   After completion, the proposed works must be maintained in a sound state of
      repair in accordance with the approved plans

5.    REFERRAL AGENCIES

Not Applicable.




                                                                                    Page 2 of 6

Used in these records

About this file

File size
41 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW14-0119 22 Seahorse Pl Noosaville.pdf · 41 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.