RA6-N Response with conditions · MCU18/0135
Attached to the e-mail SARA Response with conditions - MCU18/0135.
1809-7260 SRA
Attachment 1—Conditions to be imposed
Condition
No. Conditions
timing
Material change of use
10.4.3.1.1 Contaminated Land (unexploded ordinance) —The chief executive administering the Planning
Act 2016 nominates the Director-General of the Department of State Development, Manufacturing,
Infrastructure and Planning to be the enforcement authority for the development to which this
development approval relates for the administration and enforcement of any matter relating to the
following condition(s):
1. Provide written confirmation to the Department of State Development, Prior to
Manufacturing, Infrastructure and Planning by an approved contractor on the commencement
Australian Government, Department of Defence, Unexploded Ordnance (UXO) of works
Panel that the subject site has been remediated and cleared of Unexploded
Ordnances.
The Unexploded Ordnance (UXO) Panel is found online at:
http://www.defence.gov.au/estatemanagement/support/dehp/WhoToEngage.asp
Department of State Development, Manufacturing, Infrastructure and Planning Page 3 of 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RA6-N Response with conditions.pdfRelated documentApplication case desk ↗
About this file
- File size
- 244 KB (small file)
- File type
No other editions are linked here.