MCU14-0039 Flood report and flood man Plan rev August 2015

of 32

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (40.5 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Como Glasshouse P/L C/‐ Martoo Consulting P/L
Flood Impact Assessment – 305 Lake McDonald Drive Cooroy


1.              INTRODUCTION
1.1             Background
Water Technology Pty Ltd (WT) has been commissioned by Como Glasshouse P/L on behalf of Martoo
Consulting Pty Ltd (Martoo) to undertake a flood impact assessment and flood management plan for
an existing Greenhouse structure located at the D’VineRipe Tomato Farm, 305 Lake McDonald Drive
Cooroy.
A development application under Council file reference MCU14/0039 for a Material Change in Use
application has been previously submitted to Noosa Council in 2014. We understand that this
application was made following Council’s determination that the since constructed greenhouse at the
site was deemed to be an intensification of use and accordingly required development approval.
Council has since issued an Information Request (IR) for the application dated 25 June 2014 under
Council reference 01569. This IR requested further information against a number of items and in the
context of flooding included a flood impact assessment as well as a flood management plan under
Items 1 and 2.

1.2             Purpose and Intent
This report has been prepared to specifically address Items 1 and 2 of Council’s IR dated 25 June 2015.
Accordingly, this report has been prepared in 2 distinct chapters as follows: ‐
Chapter 2 – Flood impact assessment, which includes the following: ‐
           Background information;
           Site description;
           Summary of hydraulic modelling methodology;
           Overview of modelling results (existing and post‐developed); and
           Discussion of impacts.
Chapter 3 – Flood Management Plan, which includes the following: ‐
           Available flood warning at the site;
           Rate of rise of flooding;
           Evacuation routes and egress;
           Measures to protect the existing infrastructure during flood events; and
           Appropriate strategy and site specific measures to minimise flood risks at the site and
            potential contamination from hazardous material stored at the site.


Further details relating to the methodology and findings for the assessments are discussed separately
in the chapters of this report which follow.




3917‐01 / R01 v02 ‐ 31/08/2015                                                                       3
Log in to download the original file

MCU14-0039 Flood report and flood man Plan rev August 2015.pdf · 40.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.