07/0604 - Operational Works - Landscaping, Earthworks, Access & Frontage [As Published] · 142007.604

of 36

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

@ Page 2

based upon a visual survey of the development, it appears that the lower level deck complies with the
conditions of approval.

Nei! Blamey also noted that the ‘Driveway & Access’ Operational Works application required as part of
these conditions of approval had not been lodged. Please note that this application represents
compliance with this condition.

THE DEVELOPMENT APPLICATION

This application seeks a Development Permit for Operational Works — Landscaping, Earthworks and
Access & Frontage Works. It is sought to undertake the following work:
« Remove the existing 9m? pool located to the north of the existing dwelling;
+ Extend the northern deck towards the Bayview Road frontage by approximately 16.5m?;
+ Reconstruct the retaining wall located to the east of the existing dwelling to improve the
stability and stormwater management of the upper levels of the site. Correspondence
from Rienmac Pty Ltd detailing their recent findings regarding this structures stability is
included as Attachment 2;
+ Construct an infinity edge pool and associated overflow troughs, decks, stairs, spa and
day bed to the east of the existing dwelling:
* — Installation of three (3) above ground rainwater tanks in the south eastern corner of the
site;
+ Undertake significant landscaping works across the site to improve the movement of
surface water, buffer the visual impacts of the proposal and comply with conditions of
the previous Request for Removal of Trees.

Architectural and Landscaping Plans detailing the proposed works are included as Attachments 3 and 4.

The applicant advises that an Engineering Design and details with regard to slope stability and stormwater
run-off will be forwarded shortly. It is noted that Ashley Davey (Golder & Associates), Reinhold Koenning
(Construction Hydraulics) and Peter Rienecker (Rienmac Pty Ltd) are undertaking the preparation of this
documentation.

Further, the project builder Gordon Clements is currently preparing details with regard to construction methods
and access routes for construction equipment to the site. This will be forwarded upon completion.

Please contact our office if you require any further information and/or clarification with respect to the above
application.

Yours sincerely

JRO

Hannah Blue
Senior Planner
Martoo Consulting Pty. Ltd.

Used in these records

About this file

File size
6.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_0604 - Operational Works - Landscaping, Earthworks, Access & Frontage [As Published].pdf · 6.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.