27. LOCAL AUTHORITY BONDS
If the Local Authority has bonds associated with Building Work and the Bond has not been lodged with SBA, then the applicant will be responsible to
ensure that the relevant bond is paid before work commences on-site.

28. STANDARD CONDITION
Itis the applicants responsibility to obtain the necessary approvals from the relevant authority for removal or damage to any vegetation, which may be
necessary in order to carry out the approved works.

29. BUSHFIRE CONDITIONS — AS AT 15" OCTOBER 2009

This site has been assessed under AS3959-2009 and determined that construction for the South, East and West elevations is to Bushfire Attack
Level 29 (BAL 29) complying with Sections 3 and 5 of Standard and construction for the North elevation is to Bushfire Attack Level 19 (BAL 19)
complying with Sections 3 and 6 of Standard is required (copy of sections attached). Your window and door manufacturer must be advised of this
Bushfire Attack Level for complying frames glazing and screens to be manufactured and installed. A certificate of compliance (Form 16) will be
required at final inspection.

COUNCILS ADVISORY CONDITIONS

1. HOURS OF WORK

Environmental Protection Agency requires:

A builder or building contractor must not carry out building work on a building site in a way that makes or causes audible noise to be made from the
building work-

a) Ona Sunday or public holiday, at any time; or

b) Ona Saturday or business day, before 6.30am or after 6.30pm.

2. SILT MANAGEMENT
Provision shall be made during the construction phase to ensure that no silt, other building waste or soil leaves the allotment. Retention devices such
as silt fences, straw bales or the like are required to be installed on-site.

3. ACCESS CHAMBERS
Where stormwater access chambers occur on-site they are to remain visible at all times. If an access chamber is required to be altered in height to
accommodate proposed site works, contact the relevant Council's Sewerage Department.

SBA2017-2468 Page 7
Planning Act Form 2 — Decision notice (approval)
Version 1.0—3 July 2017
Log in to download the original file

Decision Notice.pdf · 571 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.