Our Reference: 2020-41 Council Reference: MCU21/0002 OPW21/0015 17th February 2020 Att: Tara Norley [email protected] cc: [email protected] MCU21/0002 & OPW21/0015 – Response to Information Request – 13 Vision Court Noosaville (Lot 5 SP 295958) Dear Tara, Thank you for the information request received by this office on the 2nd of February 2021. In response to the issue raised please refer below, and to the following attachments: 1. Revised Proposal Plans; 2. Revised Engineering Plans; and 3. Sustainable Building Design Code assessment table Please note this is a full response to the information request pursuant to the Development Assessment Rules. If you wish to discuss this matter further please don’t hesitate to contact me directly at your convenience. Kind Regards, Will Johnson (Town Planner) BurbDes&TownPlan (Hons) PIA.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 3 pages
Page 2
Issue – Sustainable Building Design Code Information regarding compliance with the Sustainable Building Design Code has not been provided. Information Required 1. Provide an assessment against the Sustainable Building Design Code demonstrating compliance. Response Please refer to attached assessment of the Building Design Code prepared by Building Suncoast Green. Issue – Articulation, materials and finishes The design is not considered to comply with Performance Outcome PO11 of the Medium Impact Industry Zone Code, in relation to articulation, materials and finishes, particularly in regards to the northern and western elevations. Information Required 2. Provide updated plans with additional articulation to the northern and western elevations, complying with PO11 of the Medium Impact Industry Zone Code End of applicant’s response. Response Please refer to attached plans by Building Suncoast Green which have been revised to include further articulation and visual interest to the street facing façade (north) and western façade. Issue – Mechanical plant, equipment and storage Information regarding proposed mechanical plant, equipment and storage has not been provided. Information Required 3. Provide updated proposal plans indicating proposed locations of mechanical plant, equipment and storage, in accordance with AO13.2 of the Medium Impact Industry Zone Code. Response Please refer to attached plans by Building Suncoast Green which have been revised to include a mechanical plant storage area on the roof of the building which can be accessed via pull down ladder located at the side of the building.
Page 3
Issue – Western Elevation The western elevation contains four large roller doors. It is not clear what the purpose of the roller doors is, noting that they are only accessible over proposed landscaped areas. Information Required 4. Provide clarification on the proposed roller doors on the western elevation. Response The purpose of the roller doors is to permit natural light and ventilation for the building. This is a typical design solution for larger buildings which eliminates operable windows and glass and provides a practical solution to generating passive air flow into a space. Please refer to the attached and revised plans prepared by Building Suncoast Green which include the omitted text to this effect. Issue – End of Trip Facilities The proposal is required to provide seven bicycle spaces, in accordance with the Driveways and Parking Code. It is unclear whether the ‘Bicycle Store’ indicated on the Floor Plan is sufficient in size to comply with the requirement. Information Required 5. Provide clarification on proposed bicycle spaces, in compliance with the Driveways and Parking Code. Response Please refer to the attached and revised proposal plans prepared by Building Suncoast Green which nominates a total of six (6) bicycle parking spaces split into 2 bays at either side at the rear of the tenancy. Issue – Loading Bay It is not clear that a semi-trailer can reverse into the proposed loading bay. Information Required 6. Demonstrate that, given the existing road configuration, the reverse entry manoeuvre, as detailed in AS 2890.2-2002, is achievable. Response Please refer to the attached plan prepared by Empire Engineers which demonstrates an AV can manoeuvre into the proposed loading bay.
Page 4
Issue – Waste Collection It is not clear how waste collection will be managed. Information Required 7. Noting that side lift waste collection trucks do not service on private property, provide a detailed Waste Management Plan, which must include detail, but not be limited to the following: 7.1. Number and type of bins to be collected; 7.2. Location of where bins are to be collected; 7.3. Demonstrate how stormwater will not enter the wash bin area; 7.4. Provide details of the bin wash area’s connection to sewer infrastructure; 7.5. Type of vehicle required for the collection; 7.6. Provide travel paths for the required waste collection vehicle, demonstrating how it will manoeuvre on site without having to use more than a 3 point turn to turn around. Response 7.1. Number and type of bins to be collected; The proposed bin enclosure has been designed to accommodate 2 x 1.1m3 bins which can be collected via a front collection WCV. If 2 x 1.1m3 cubic bins are not considered suitable by the future tenant of the premises than the equivalent quantity of 240L bins will be requested and utilized. 7.2. Location of where bins are to be collected; In the proposed screened bin enclosure located in the front north-east corner of the site adjacent to the driveway. 7.3. Demonstrate how stormwater will not enter the wash bin area; Please refer to the attached and revised Building Design and Civil Design plans which highlight a bunded wash down pit, the bunded sides ensure stormwater cannot access the pit which is only intended for bin wash down. 7.4. Provide details of the bin wash area’s connection to sewer infrastructure; As above and per attached and revised Civil Design plans prepared by Empire Engineers. 7.5. Type of vehicle required for the collection; Front loaded WCV if 1.1m3 cubic bins utilized, alternatively side collection (kerb collection) WCV if 240L wheelie bins utilized. 7.6. Provide travel paths for the required waste collection vehicle, demonstrating how it will manoeuvre on site without having to use more than a 3 point turn to turn around. As per advice note provided, it is understood waste collection vehicles do not service on private property, however the attached vehicle movement analysis within the Civil Design plans demonstrates access and egress can occur if need be. We trust the above and attached documents can assist Council in finalising this application and hope for a prompt decision.