Attachment 1 - Amended Construction and Tree Management Plan · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
Very large file (10.8 MB): may take a few minutes to open.
Stage 2 Construction (Cabins 1, 10 &11, 12-15) – Refer ATTACHMENT D
Following the completion of Stage 1, construction will shift to Stage 2.
Stage 2 includes: Cabins 1, 10 & 11, 12 & 13, 14 & 15. This stage will also include the completion of the
boardwalks and interior fit outs for the Stage 1 cabins.
This phase will involve similar steps as Stage 1, including earthworks, foundations, structural framing,
roofing and cladding, plus the addition of interior fit-outs, services and boardwalk construction.
Throughout the construction process, regular monitoring and adjustments will be made to ensure
compliance and the tree protection measures and environmental guidelines as previously identified and
detailed.
Stage 3 Construction (Carpark and Boardwalks) – Refer ATTACHMENT D
Following the completion of Stage 1 & Stage 2, construction will shift to Stage 3
Stage 3 includes:
o Boardwalks to the remaining cabins, car parking and access routes.
o Removal of Temporary utilities and the connection of permanent services to the council systems.
o Final Commissioning of all cabins and handover procedures.
This phase will also include the demobilisation of construction site facilities and site
rectification/rehabilitation - as detailed in the section Post Construction.
5.2. Cabin Construction Methodology:
General Earthworks and Excavation:
Excavation will be limited to the necessary extent, focusing on areas where foundation elements are to be
placed.
In sensitive areas, hand excavation will be used to minimize soil disturbance and root damage. Where
mechanical excavation is required, low-impact machinery will be used, and ground protection measures
will be implemented.
Refer to ATTACHMENT C - Work Methodologies Adjacent Trees for detailed information on:
o General Excavation Methodologies
o Post Hole Dig Works Methodology
Excavated soil will be stockpiled in designated areas, away from sensitive vegetation and watercourses.
Whenever feasible, excavated soil will be reused on-site to minimize the need for imported fill. Soil
stabilization techniques will be implemented to prevent erosion and promote vegetation growth.
Effective stormwater management measures, such as silt fences, sediment traps, and swales, will be
implemented to control runoff and prevent sedimentation.
Regular monitoring of water quality will be conducted to ensure compliance with environmental
regulations.
Foundations:
As part of the project design process, a light touch on the ground is the intention, which has driven the
construction methodology and the proposed cabin designs.
It is proposed that a prefabricated steel support sub-frame on pier foundations (either bored piers or screw
piers, whichever is deemed the least invasive at each location required) be used to construct the cabins
within a few meters of retained trees without overly compromising the tree root systems or the ground in
Construction and Tree Management Plan - REV03 Page 55 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 1 - Amended Construction and Tree Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.