6.6 POST-CONSTRUCTION
6.1.   Site Demobilisation
              Post Stage 3 Carpark and Road completion, the remaining Site Set-up and Contractors' facilities will be
               removed from the site, this could include the removal of:
               o Construction site offices and amenities.
               o Laydown Areas.
               o Site Fencing; and
               o Tree Protection Fencing.
              Removal of all temporary utilities and the connection of permanent services to council systems.

6.2.   Environmental Rehabilitation and Landscaping
              Post site demobilisation, the rehabilitation of all impacted areas to be completed.
              Guidance will be available from the project arborist and ecologist.
              All works are to be completed as detailed by the site-based rehabilitation and landscaping plans.
              Monitoring and reporting by contractors and the project ecologist regarding the rehabilitation progress.

6.3.   Post Construction Arborist Report
              A Post Construction Arborist Report will be prepared by the Project Arborist for the retained trees. A Visual
               Tree Assessment will be carried out detailing each tree's condition and vigour, damage or disturbance
               which may have occurred, and remedial works undertaken.
              The Project Arborist may at any time implement new or additional procedures as may be required for the
               site in the best interest of the trees and the development as a whole.

6.4.   Hand-Over Documentation
              After the final inspection, a Certification of Compliance shall be supplied by the Project Arborist for the
               retained trees along with any monitoring or deviation documentation as required.
              Detailed instructional information will be handed over to the resort management team to ensure the
               ongoing site maintenance and protection measures.
              This will then be included in the RACV Resort’s current and ongoing tree maintenance strategy including
               the Native Foresters’ Weed & Rehabilitation Management Plan.




Construction and Tree Management Plan - REV03                                                                Page 59 of 45

Used in these records

About this file

File size
10.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 1 - Amended Construction and Tree Management Plan.pdf · 10.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.