3.6 MANAGEMENT PLAN STRUCTURE
This Construction and Tree Management Plan outlines a comprehensive approach to the construction and development
of the proposed RACV project, prioritizing the preservation of the site's natural environment, minimizing ecological impact
and protecting individual trees of value as required by the development approval.

The report is a collaborative effort between Aspect Architects & Project Managers and Consult Arborist, incorporating
expertise from various disciplines, including ecology, arboriculture, construction management, and engineering.
Gondwana Ecology Group have provided a review from an ecological perspective, and MRP Hydraulic and Fire services
Consultants have provided information on the proposed construction methodology for the provision of water, sewer and
fire services.

Key strategies include careful site planning, staged construction, specialised construction techniques and the
implementation of stringent environmental protection measures. By staging the construction into three phases, and
facilitating the use of smaller, less disruptive construction equipment and construction works, the overall impact on the
site will be reduced considerably. In addition, this staged process with smaller construction areas and specialised building
techniques allows for better onsite environmental controls.

The project works have been separated into (1) PRE-CONSTRCTION, (2) CONSTRUCTION, and (3) POST
CONSTRUCTION. A series of ONGOING TASKS (i.e. to ensure compliance and tree protection) occurs throughout all
three stages.

PRE-CONSTRUCTION

       Tree Protection Measures
       Construction Contract
       Collaboration and Education
       Site Readiness
       Site Set-up and Preparation


CONSTRUCTION

       Overall Project Construction Sequencing/Stage of Works
       Cabin Construction Methodology


POST- CONSTRUCTION

       Site Demobilisation
       Rehabilitation and Landscaping
       Post Construction Arborist Report
       Hand-Over Documentation

The ONGOING TASKS include:

       Collaboration


Construction and Tree Management Plan - REV03                                                                 Page 8 of 45

Used in these records

About this file

File size
10.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 1 - Amended Construction and Tree Management Plan.pdf · 10.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.